UNION OF INDIA THROUGH THE GENERAL MANAGER CENTRAL RAILWAY AND ORS vs DIGAMBAR VISHWANATH DEOKATE AND OTHER — CA/9130/2023
Case under Land Acquisition Act - Appeal Section 18. Disposed: --DISMISSED on 04th May 2026.
CNR: HCBM030287062023
e-Filing Number
15-07-2023
Filing Number
CA/21605/2023
Filing Date
15-Jul-2023
Registration No
CA/9130/2023
Registration Date
25-Jul-2023
Judge
Hon'ble Shri Justice Shailesh P. Brahme
Coram
Hon'ble Shri Justice Shailesh P. Brahme
Bench Type
Single
Judicial Branch
Civil
Decision Date
04-May-2026
Nature of Disposal
--DISMISSED
Last updated 15-Jun-2026
Acts & Sections
Petitioner(s)
-
1.UNION OF INDIA THROUGH THE GENERAL MANAGER CENTRAL RAILWAY AND ORS
Adv. Talhar Ajay G.
-
2.THE DEPUTY CHIEF ENGINEER CONSTRUCTION CENTRAL RAILWAY
-
3.THE STATE OF MAHARASHTRA THROUGH ITS COLLECTOR BEED
-
4.THE DEPUTY COLLECTOR LAND ACQUISITION JAYKWADI PROJECT DIIST BEED THROUGH THE COLLECTOR BEED
Respondent(s)
-
1.DIGAMBAR VISHWANATH DEOKATE AND OTHER
-
2.SHRINIVAS VISHWANATH DEOKATE
Case History
-
Case disposedDisposed
-
04-May-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
Case Summary: CA/9130/2023 The High Court of Bombay (Aurangabad Bench) dismissed the Union of India's appeals challenging land acquisition compensation rates for a railway project from Ahmednagar-Beed-Parli. The Reference Court had enhanced compensation from Rs. 900-1,500 per acre to Rs. 3,750-5,625 per acre based on comparable sale deeds from the same village. The court upheld this enhancement as reasonable, supported by credible evidence (Exhibit 27), and within the four-fold limit prescribed by government resolution. Statutory benefits under Section 23(1-A) were also upheld as lawful. This case analysis is maintained by casestatus.in based on publicly available court records.
-
30-Mar-2026
For Orders
Hon'ble Shri Justice Shailesh P. Brahme
-
05-Mar-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
-
05-Mar-2026
For Orders
Hon'ble Shri Justice Shailesh P. Brahme
-
13-Dec-2023
Hon'ble Shri Justice Arun R. PednekerView PDF
-
13-Dec-2023
For Orders
Hon'ble Shri Justice Arun R. Pedneker
-
20-Sep-2023
Hon'ble Shri Justice Arun R. PednekerView PDF
-
20-Sep-2023
First hearing
Initial hearing scheduled
-
15-Jul-2023
Case filed
Registration No. CA/9130/2023
Case Summary: CA/9130/2023 The High Court of Bombay (Aurangabad Bench) dismissed the Union of India's appeals challenging land acquisition compensation rates for a railway project from Ahmednagar-Beed-Parli. The Reference Court had enhanced compensation from Rs. 900-1,500 per acre to Rs. 3,750-5,625 per acre based on comparable sale deeds from the same village. The court upheld this enhancement as reasonable, supported by credible evidence (Exhibit 27), and within the four-fold limit prescribed by government resolution. Statutory benefits under Section 23(1-A) were also upheld as lawful. This case analysis is maintained by casestatus.in based on publicly available court records.