UNION OF INDIA THROUGH THE GENERAL MANAGER CENTRAL RAILWAY AND ORS vs VIVEKSAGAR GANPAT HONDRE AND OTHERS — FA/90/2024
Case under Land Acquisition Act - Appeal Section 18. Disposed: --DISMISSED on 04th May 2026.
CNR: HCBM030286992023
e-Filing Number
15-07-2023
Filing Number
FA/21599/2023
Filing Date
15-Jul-2023
Registration No
FA/90/2024
Registration Date
03-Jan-2024
Judge
Hon'ble Shri Justice Shailesh P. Brahme
Coram
Hon'ble Shri Justice Shailesh P. Brahme
Bench Type
Single
Judicial Branch
Civil
Decision Date
04-May-2026
Nature of Disposal
--DISMISSED
Last updated 15-Jun-2026
Acts & Sections
Petitioner(s)
-
1.UNION OF INDIA THROUGH THE GENERAL MANAGER CENTRAL RAILWAY AND ORS
Adv. Talhar Ajay G.
-
2.THE DEPUTY CHIEF ENGINEER CONSTRUCTION CENTRAL RAILWAY
-
3.THE STATE OF MAHARASHTRA THROUGH ITS COLLECTOR BEED
-
4.THE DEPUTY COLLECTOR LAND ACQUISITION J P 2 DIST BEED THROUGH THE COLLECTOR BEED
Respondent(s)
-
1.VIVEKSAGAR GANPAT HONDRE AND OTHERS
-
2.VISHWANATH GANPAT HONDRE
-
3.RAMLING GANPAT HONDRE
Case History
-
Case disposedDisposed
-
04-May-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
Summary of FA/90/2024 The High Court of Bombay at Aurangabad dismissed the Union of India's appeals challenging a Reference Court's award for land acquisition in Dhekanmoha village for a railway project. The court upheld the Reference Court's enhanced compensation rates (Rs. 3750/- per bigha for Jirayat land, Rs. 5625/- for irrigated land) based on compatible sale deed evidence, finding the rates reasonable and within legal limits under Maharashtra's Government Resolution. The court also upheld statutory benefits under Section 23(1-A) of the Land Acquisition Act, directing immediate disbursement of deposited amounts with accrued interest to the claimants. This case analysis is maintained by casestatus.in based on publicly available court records.
-
30-Mar-2026
For Orders
Hon'ble Shri Justice Shailesh P. Brahme
-
05-Mar-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
-
05-Mar-2026
First hearing
Initial hearing scheduled
-
12-Feb-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
-
08-May-2024
Hon'ble Shri Justice S. G. MehareView PDF
-
15-Jul-2023
Case filed
Registration No. FA/90/2024
Summary of FA/90/2024 The High Court of Bombay at Aurangabad dismissed the Union of India's appeals challenging a Reference Court's award for land acquisition in Dhekanmoha village for a railway project. The court upheld the Reference Court's enhanced compensation rates (Rs. 3750/- per bigha for Jirayat land, Rs. 5625/- for irrigated land) based on compatible sale deed evidence, finding the rates reasonable and within legal limits under Maharashtra's Government Resolution. The court also upheld statutory benefits under Section 23(1-A) of the Land Acquisition Act, directing immediate disbursement of deposited amounts with accrued interest to the claimants. This case analysis is maintained by casestatus.in based on publicly available court records.