THE EXECUTIVE ENGINEER, LATUR MEDIUM PROJECT vs DILIP SHRIRANG JADHAV AND ANR — FA/1376/2012
Case under Land Acquisition Act - Appeal. Disposed: Contested--DISPOSED OFF on 23rd April 2026.
CNR: HCBM030255732011
Filing Number
FA/20710/2011
Filing Date
12-Aug-2011
Registration No
FA/1376/2012
Registration Date
10-Aug-2012
Judge
Hon'ble Shri Justice Arun R. Pedneker
Coram
Hon'ble Shri Justice Arun R. Pedneker
Bench Type
Single
Judicial Branch
Civil
Decision Date
23-Apr-2026
Nature of Disposal
Contested--DISPOSED OFF
Last updated 28-May-2026
Acts & Sections
Petitioner(s)
-
1.THE EXECUTIVE ENGINEER, LATUR MEDIUM PROJECT
Adv. GANGWAL MADHUBALA BHARAT
Respondent(s)
-
1.DILIP SHRIRANG JADHAV AND ANR
Adv. GP FOR R/2,COPY NOT SERVED ON GP 1123
Case History
-
Case disposedDisposed
-
24-Apr-2026
For Hearing & Final Disposal (High On Board)
Hon'ble Shri Justice Arun R. Pedneker
-
23-Apr-2026
Hon'ble Shri Justice Arun R. PednekerView PDF
The High Court of Bombay at Aurangabad allowed the land acquisition appeals filed by claimants Dilip Shrirang Jadhav and others against the Latur Medium Project, enhancing compensation rates based on findings that the acquired lands possessed good quality and fertility despite being classified as Jirayat (rain-fed). The court increased compensation by 40% to Rs. 13,447 per Are and directed the State to deposit the balance amount within eight weeks, while dismissing the Acquiring Body's appeals. This case analysis is maintained by casestatus.in based on publicly available court records.
-
23-Apr-2026
For Orders
Hon'ble Shri Justice Sanjay A. Deshmukh
-
17-Apr-2026
Hon'ble Shri Justice Sanjay A. DeshmukhView PDF
-
17-Mar-2026
For Orders
Hon'ble Shri Justice Sanjay A. Deshmukh
-
17-Feb-2026
For Orders
Hon'ble Shri Justice Sanjay A. Deshmukh
-
11-Dec-2025
For Orders
Hon'ble Shri Justice Sanjay A. Deshmukh
-
04-Dec-2025
Hon'ble Shri Justice Sanjay A. DeshmukhView PDF
-
11-Nov-2025
For Orders
Hon'ble Shri Justice R. M. Joshi
-
10-Oct-2025
For Orders
Hon'ble Shri Justice Kishore C. Sant
-
28-Apr-2022
For Orders
Hon'ble Shri Justice Shrikant D. Kulkarni
-
11-Mar-2022
Hon'ble Shri Justice Shrikant D. KulkarniView PDF
-
07-Feb-2022
For Orders
Hon'ble Shri Justice Vinay Joshi
-
25-Feb-2020
Urgent Orders (Civil)
Hon'ble Shri Justice K. K. Sonawane
-
02-Apr-2019
For Final Hearing -CIVIL
Hon'ble Shri Justice V.L. Achliya
-
13-Aug-2012
Hon'ble Shri Justice S V GangapurwalaView PDF
-
13-Aug-2012
First hearing
Initial hearing scheduled
-
12-Aug-2011
Case filed
Registration No. FA/1376/2012
The High Court of Bombay at Aurangabad allowed the land acquisition appeals filed by claimants Dilip Shrirang Jadhav and others against the Latur Medium Project, enhancing compensation rates based on findings that the acquired lands possessed good quality and fertility despite being classified as Jirayat (rain-fed). The court increased compensation by 40% to Rs. 13,447 per Are and directed the State to deposit the balance amount within eight weeks, while dismissing the Acquiring Body's appeals. This case analysis is maintained by casestatus.in based on publicly available court records.