SHAHIDAS TRIMBAK MHASKE vs THE STATE OF MAHARASHTRA AND ORS — FA/2637/2022
Case under Land Acquisition Act - Appeal Section 18. Next hearing: 17th June 2026.
CNR: HCBM030255432019
Filing Number
FA/19532/2019
Filing Date
29-Jun-2019
Registration No
FA/2637/2022
Registration Date
27-Sep-2022
Judge
Hon'ble Shri Justice Neeraj P. Dhote
Coram
Hon'ble Shri Justice Neeraj P. Dhote
Bench Type
Single
Category
LAND ACQUISITION/REQUISITION(CENTRAL/STATE) ( 20 )
Sub-Category
COMPENSATION ( 8 )
Judicial Branch
Civil
Last updated 18-Jun-2026
Acts & Sections
Petitioner(s)
-
1.SHAHIDAS TRIMBAK MHASKE
Adv. KAKADE DEEPAK M.
Respondent(s)
-
1.THE STATE OF MAHARASHTRA AND ORS
Case History
-
17-Jun-2026
Next hearingPending
-
17-Jun-2026
Hon'ble Shri Justice Neeraj P. DhoteView PDF
Summary of FA/2637/2022 Shahidas Trimbak Mhaske v. The State of Maharashtra The appeal was partly allowed. The appellant's land, acquired for the Nimna Dudhana Project in Jalna, was entitled to enhanced compensation on parity grounds: Rs.4,426/- per R for dry land and Rs.6,629/- per R for seasonally irrigated land. However, the court rejected the claim to classify the entire Gat No.50/C as fully irrigated land due to lack of evidence regarding irrigation infrastructure, and the original reference court's findings were upheld. Interest applicable from the final award date per applicable precedent. This case analysis is maintained by casestatus.in based on publicly available court records.
-
17-Jun-2026
—
Hon'ble Shri Justice Siddheshwar Sundarrao Thombre
-
17-Jun-2026
—
Hon'ble Shri Justice Siddheshwar Sundarrao Thombre
-
16-Apr-2026
For Orders
Hon'ble Shri Justice Siddheshwar Sundarrao Thombre
-
09-Apr-2026
—
Hon'ble Shri Justice Siddheshwar Sundarrao Thombre
-
13-Dec-2025
For Settlement - B
Lok Adalat
-
08-Jul-2019
First hearing
Initial hearing scheduled
-
29-Jun-2019
Case filed
Registration No. FA/2637/2022
Summary of FA/2637/2022 Shahidas Trimbak Mhaske v. The State of Maharashtra The appeal was partly allowed. The appellant's land, acquired for the Nimna Dudhana Project in Jalna, was entitled to enhanced compensation on parity grounds: Rs.4,426/- per R for dry land and Rs.6,629/- per R for seasonally irrigated land. However, the court rejected the claim to classify the entire Gat No.50/C as fully irrigated land due to lack of evidence regarding irrigation infrastructure, and the original reference court's findings were upheld. Interest applicable from the final award date per applicable precedent. This case analysis is maintained by casestatus.in based on publicly available court records.