National Highways Authority of India PIU Jalgaon MANORKAR DEEPAK SURESH vs Chandrakant Govinda Dutte And Another — CA/9158/2025

Disposed: --DISPOSED OFF on 09th April 2026.

Case disposed

CNR: HCBM030221892025

e-Filing Number

07-02-2025

Filing Number

CA/16551/2025

Filing Date

09-Jun-2025

Registration No

CA/9158/2025

Registration Date

21-Aug-2025

Judge

Hon'ble Shri Justice Arun R. Pedneker

Coram

Hon'ble Shri Justice Arun R. Pedneker

Bench Type

Single

Judicial Branch

Civil

Decision Date

09-Apr-2026

Nature of Disposal

--DISPOSED OFF

Last updated 26-May-2026

Petitioner(s)

  1. 1.National Highways Authority of India PIU Jalgaon MANORKAR DEEPAK SURESH

Respondent(s)

  1. 1.Chandrakant Govinda Dutte And Another

    Adv. ,BHOSALE RAMDAS B.,Kale Ajeet B.,ADV. AJIT B. KALE FOR R/1 (VP FILED),ADV. N. S. SALUNKE FOR R/2 (NOA FILED) 1123

  2. 2.The Competent Authority Land Acquisition And Sub Divisional Officer At Bhusawal

Case History

  1. Case disposedDisposed

  2. 15-Apr-2026

    Hon'ble Shri Justice Arun R. PednekerView PDF

  3. 09-Apr-2026

    Hon'ble Shri Justice Arun R. PednekerView PDF

  4. 09-Apr-2026

    Hon'ble Shri Justice Arun R. PednekerView PDF

    Summary The Bombay High Court (Aurangabad Bench) dismissed multiple arbitration appeals filed by the National Highways Authority of India challenging compensation awards for land acquired in villages Ghodasgaon and Muktainagar for NH-6 expansion. The court upheld the arbitrator's compensation of Rs. 2,600 per sq. mtr., finding that sufficient deductions were made for distance and land size, and that the arbitration awards were reasonable and properly considered the national highway potential of the acquired lands. This case analysis is maintained by casestatus.in based on publicly available court records.

  5. 09-Apr-2026

    Revoked

    Hon'ble Shri Justice Shailesh P. Brahme

  6. 11-Feb-2026

    For Admission - After Notice

    Hon'ble Shri Justice Arun R. Pedneker

  7. 12-Nov-2025

    Hon'ble Shri Justice Arun R. PednekerView PDF

  8. 29-Sep-2025

    Hon'ble Shri Justice R. M. JoshiView PDF

  9. 29-Sep-2025

    First hearing

    Initial hearing scheduled

  10. 22-Aug-2025

    Hon'ble Shri Justice Rohit W. JoshiView PDF

  11. 09-Jun-2025

    Case filed

    Registration No. CA/9158/2025

casestatus.in Summary

Summary The Bombay High Court (Aurangabad Bench) dismissed multiple arbitration appeals filed by the National Highways Authority of India challenging compensation awards for land acquired in villages Ghodasgaon and Muktainagar for NH-6 expansion. The court upheld the arbitrator's compensation of Rs. 2,600 per sq. mtr., finding that sufficient deductions were made for distance and land size, and that the arbitration awards were reasonable and properly considered the national highway potential of the acquired lands. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts

Search Another Case