NATIONAL HIGHWAYS AUTHORITY OF INDIA PIU,JALGAON THROUGH PROJECT DIRECTOR SHIVAJI V PAWAR MANORKAR DEEPAK SURESH vs JANKIRAM FATRU DHAYDE AND ANOTHER — ARBA/75/2026
Case under Arbitration and Concilation Act 1996 Section 37. Disposed: Contested--DISPOSED OFF on 09th April 2026.
CNR: HCBM030119842025
e-Filing Number
06-02-2025
Filing Number
ARBA/9111/2025
Filing Date
20-03-2025
Registration No
ARBA/75/2026
Registration Date
04-04-2026
Judge
HON'BLE SHRI JUSTICE ARUN R. PEDNEKER
Coram
HON'BLE SHRI JUSTICE ARUN R. PEDNEKER
Bench Type
Single
Judicial Branch
Civil
Decision Date
09th April 2026
Nature of Disposal
Contested--DISPOSED OFF
Acts & Sections
Petitioner(s)
NATIONAL HIGHWAYS AUTHORITY OF INDIA PIU,JALGAON THROUGH PROJECT DIRECTOR SHIVAJI V PAWAR MANORKAR DEEPAK SURESH
Respondent(s)
JANKIRAM FATRU DHAYDE AND ANOTHER
Adv. ,BAGUL RAHUL BHAGAWANTRAO,ADV. A. B. KALE FOR R/NO.1 1123
The Competent Authority Land Acquisition And Sub Divisional Officer At Bhusawal
Adv. ADV. RAHUL B. BAGUL FOR R/2 (NOA FILED),BAGUL RAHUL BHAGAWANTRAO
Hearing History
Judge: HON'BLE SHRI JUSTICE ARUN R. PEDNEKER
OBJECTIONS NOT REMOVED (FIRST TIME)
PETITIONS FOR ADMISSION - FRESH - CIVIL SIDE MATTERS
| Date | Purpose |
|---|---|
| 17-04-2025 | OBJECTIONS NOT REMOVED (FIRST TIME) |
| 09-04-2026 | PETITIONS FOR ADMISSION - FRESH - CIVIL SIDE MATTERS |
Orders
Summary The High Court of Bombay (Aurangabad Bench) dismissed multiple arbitration appeals filed by the National Highways Authority of India challenging land compensation awards for NH-6 expansion near Jalgaon. The court upheld the arbitrator's compensation of Rs. 2,600 per sq. meter, finding that adequate deductions were made for distance and land size factors, and that the arbitrator properly considered post-notification sale evidence and National Highway acquisition potential in determining fair market value. This case analysis is maintained by casestatus.in based on publicly available court records.
Summary The High Court of Bombay (Aurangabad Bench) dismissed multiple arbitration appeals filed by the National Highways Authority of India challenging land compensation awards for NH-6 expansion near Jalgaon. The court upheld the arbitrator's compensation of Rs. 2,600 per sq. meter, finding that adequate deductions were made for distance and land size factors, and that the arbitrator properly considered post-notification sale evidence and National Highway acquisition potential in determining fair market value. This case analysis is maintained by casestatus.in based on publicly available court records.