THE MAHARASHTRA KRUSHNA VALLEY DEVELOPMENT CO. THR EX. ENGINEER, MEDIUM PROJECT OSMANABAD AND ORS. vs GOKUL VISHWANATH SHINDE AND ANR. — CA/2388/2026
Case under Land Acquisition Act - Appeal Section 18. Disposed: --Admitted/Allowed/Granted/Rule Absolute on 06th May 2026.
CNR: HCBM030083942026
Filing Number
CA/6248/2026
Filing Date
25-Feb-2026
Registration No
CA/2388/2026
Registration Date
26-Feb-2026
Judge
Hon'ble Shri Justice Siddheshwar Sundarrao Thombre
Coram
Hon'ble Shri Justice Siddheshwar Sundarrao Thombre
Bench Type
Single
Judicial Branch
Civil
Decision Date
06-May-2026
Nature of Disposal
--Admitted/Allowed/Granted/Rule Absolute
Last updated 14-Jun-2026
Acts & Sections
Petitioner(s)
-
1.THE MAHARASHTRA KRUSHNA VALLEY DEVELOPMENT CO. THR EX. ENGINEER, MEDIUM PROJECT OSMANABAD AND ORS.
Adv. Gaikwad Anil M.
Respondent(s)
-
1.GOKUL VISHWANATH SHINDE AND ANR.
Case History
-
Case disposedDisposed
-
06-May-2026
Hon'ble Shri Justice Siddheshwar Sundarrao ThombreView PDF
Case Summary: CA/2388/2026 The High Court of Bombay (Aurangabad Bench) allowed the Maharashtra Krishna Valley Development Co.'s application to condon a 1215-day delay in filing restoration applications for two First Appeals (Nos. 5258/2022 and 5237/2022), set aside the October 18, 2022 order, and restored both appeals for hearing. The court also permitted withdrawal of 75% of the deposited amount with accrued interest and allowed impleadment of a previously omitted party. This case analysis is maintained by casestatus.in based on publicly available court records.
-
06-May-2026
For Orders
Hon'ble Shri Justice Shailesh P. Brahme
-
30-Mar-2026
First hearing
Initial hearing scheduled
-
04-Mar-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
-
25-Feb-2026
Case filed
Registration No. CA/2388/2026
Case Summary: CA/2388/2026 The High Court of Bombay (Aurangabad Bench) allowed the Maharashtra Krishna Valley Development Co.'s application to condon a 1215-day delay in filing restoration applications for two First Appeals (Nos. 5258/2022 and 5237/2022), set aside the October 18, 2022 order, and restored both appeals for hearing. The court also permitted withdrawal of 75% of the deposited amount with accrued interest and allowed impleadment of a previously omitted party. This case analysis is maintained by casestatus.in based on publicly available court records.