SAKHARAM KRISHNAJI VAIDYA vs THE STATE OF MAH AND ANR — CA/4022/2017

Case under Land Acquisition Act - Appeal. Disposed: --Admitted/Allowed/Granted/Rule Absolute on 02nd April 2026.

Case disposed Next hearing 05-Mar-2020

CNR: HCBM030057942016

Filing Number

CA/4509/2016

Filing Date

10-Feb-2016

Registration No

CA/4022/2017

Registration Date

23-Mar-2017

Judge

Hon'ble Shri Justice Sanjay A. Deshmukh

Coram

Hon'ble Shri Justice Sanjay A. Deshmukh

Bench Type

Single

Judicial Branch

Civil

Decision Date

02-Apr-2026

Nature of Disposal

--Admitted/Allowed/Granted/Rule Absolute

Last updated 24-Apr-2026

Acts & Sections

Land Acquisition Act - Appeal

Petitioner(s)

  1. 1.SAKHARAM KRISHNAJI VAIDYA

    Adv. BHOKARIKAR MADHAV M.

Respondent(s)

  1. 1.THE STATE OF MAH AND ANR

    Adv. G.P. FOR R/1 1123

Case History

  1. Case disposedDisposed

  2. 02-Apr-2026

    Hon'ble Shri Justice Sanjay A. DeshmukhView PDF

    Case Summary The High Court of Bombay at Aurangabad partially allowed three land acquisition appeals regarding compensation for agricultural land acquired for the Hatnoor project canal construction. The court enhanced the compensation from Rs.266-750 per acre (awarded by the Land Reference Court) to Rs.57 per square meter, applying 50% cumulative escalation based on precedent judgments recognizing the lands' non-agricultural (N.A.) development potential. The enhanced compensation with statutory benefits must be deposited within six months. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 02-Apr-2026

    For Orders

    Hon'ble Shri Justice Sanjay A. Deshmukh

  4. 30-Mar-2026

    For Orders

    Hon'ble Shri Justice Sanjay A. Deshmukh

  5. 30-Mar-2026

    For Orders

    Hon'ble Shri Justice Sanjay A. Deshmukh

  6. 26-Mar-2026

    Hon'ble Shri Justice Sanjay A. DeshmukhView PDF

  7. 25-Mar-2026

    For Orders

    Hon'ble Shri Justice Sanjay A. Deshmukh

  8. 17-Mar-2026

    Hon'ble Shri Justice Sanjay A. DeshmukhView PDF

  9. 17-Mar-2026

    For Orders

    Hon'ble Shri Justice Sanjay A. Deshmukh

  10. 11-Mar-2026

    Hon'ble Shri Justice Sanjay A. DeshmukhView PDF

  11. 11-Mar-2026

    For Orders

    Hon'ble Shri Justice Sanjay A. Deshmukh

  12. 07-Mar-2026

    Hon'ble Shri Justice Sanjay A. DeshmukhView PDF

  13. 07-Mar-2026

    For Orders

    Hon'ble Shri Justice Sanjay A. Deshmukh

  14. 20-Feb-2026

    Hon'ble Shri Justice Sanjay A. DeshmukhView PDF

  15. 20-Feb-2026

    For Orders

    Hon'ble Shri Justice Sanjay A. Deshmukh

  16. 12-Feb-2026

    For Orders

    Hon'ble Shri Justice Sanjay A. Deshmukh

  17. 05-Feb-2026

    For Orders

    Hon'ble Shri Justice Sanjay A. Deshmukh

  18. 27-Jan-2026

    Hon'ble Shri Justice Sanjay A. DeshmukhView PDF

  19. 27-Jan-2026

    For Orders

    Hon'ble Shri Justice Sanjay A. Deshmukh

  20. 18-Nov-2025

    For Orders

    Hon'ble Shri Justice R. M. Joshi

  21. 06-Oct-2025

    For Orders

    Hon'ble Shri Justice Kishore C. Sant

  22. 28-Jul-2025

    Hon'ble Shri Justice Kishore C. SantView PDF

  23. 08-Dec-2022

    For Orders

    Hon'ble Shri Justice S. G. Dige

  24. 13-Oct-2022

    For Orders

    Hon'ble Shri Justice S. G. Dige

  25. 30-Jul-2021

    For Admission - After Notice

    Hon'ble Shri Justice R. G. Avachat

  26. 30-Apr-2021

    For Admission - After Notice

    Hon'ble Shri Justice Anil S. Kilor

  27. 09-Apr-2021

    For Admission - After Notice

    Hon'ble Shri Justice Anil S. Kilor

  28. 22-Mar-2021

    For Admission - Fresh

    Hon'ble Shri Justice Anil S. Kilor

  29. 04-Jan-2021

    For Hearing & Final Disposal

    Hon'ble Shri Justice V.K. Jadhav

  30. 05-Mar-2020

    First hearing

    Initial hearing scheduled

  31. 26-Sep-2019

    Hon'ble Smt. Justice Vibha KankanwadiView PDF

  32. 10-Feb-2016

    Case filed

    Registration No. CA/4022/2017

casestatus.in Summary

Case Summary The High Court of Bombay at Aurangabad partially allowed three land acquisition appeals regarding compensation for agricultural land acquired for the Hatnoor project canal construction. The court enhanced the compensation from Rs.266-750 per acre (awarded by the Land Reference Court) to Rs.57 per square meter, applying 50% cumulative escalation based on precedent judgments recognizing the lands' non-agricultural (N.A.) development potential. The enhanced compensation with statutory benefits must be deposited within six months. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts

Search Another Case