National Highways Authority of India Through its Project Director Amrish M Mankar RAHATE SATYAJEET JADHAVRAO vs Mohd Isaq Gulab Patel and Another — CA/3441/2026

Case under Arbitration and Concilation Act 1996 Section 37. Next hearing: 07th April 2026.

Next hearing 07-Apr-2026

CNR: HCBM030035482026

e-Filing Number

21-01-2026

Filing Number

CA/2652/2026

Filing Date

22-Jan-2026

Registration No

CA/3441/2026

Registration Date

23-Mar-2026

Judge

Hon'ble Shri Justice Arun R. Pedneker

Coram

Hon'ble Shri Justice Arun R. Pedneker

Bench Type

Single

Judicial Branch

Civil

Last updated 08-Apr-2026

Acts & Sections

Arbitration and Concilation Act 1996 Section 37

Petitioner(s)

  1. 1.National Highways Authority of India Through its Project Director Amrish M Mankar RAHATE SATYAJEET JADHAVRAO

Respondent(s)

  1. 1.Mohd Isaq Gulab Patel and Another

  2. 2.The Competent Authority Land Acquisition Aurangabad

Case History

  1. 07-Apr-2026

    Next hearingPending

  2. 30-Mar-2026

    For Orders

    Hon'ble Shri Justice Arun R. Pedneker

  3. 24-Mar-2026

    Hon'ble Shri Justice Arun R. PednekerView PDF

    Summary: The High Court of Judicature at Bombay, Aurangabad Bench, issued a preliminary order in six consolidated arbitration appeals (ARBA/50-55/2026) filed by the National Highways Authority of India regarding land acquisition matters from villages Talesaman and Deolai. Notices were issued to respondents returnable on 27.03.2026, with counsel waiving service. The court permitted NHAI to deposit the differential amount with interest by 27.03.2026 and granted liberty to file withdrawal applications. This case analysis is maintained by casestatus.in based on publicly available court records.

  4. 22-Jan-2026

    Case filed

    Registration No. CA/3441/2026

casestatus.in Summary

Summary: The High Court of Judicature at Bombay, Aurangabad Bench, issued a preliminary order in six consolidated arbitration appeals (ARBA/50-55/2026) filed by the National Highways Authority of India regarding land acquisition matters from villages Talesaman and Deolai. Notices were issued to respondents returnable on 27.03.2026, with counsel waiving service. The court permitted NHAI to deposit the differential amount with interest by 27.03.2026 and granted liberty to file withdrawal applications. This case analysis is maintained by casestatus.in based on publicly available court records.