The Executive Engineer, Patbandhare Project Majbutikaran Division, Omerga, Tq. Omerga, Dist. Osmana Satish Bappasaheb Parnere vs Hussain Abdul Jamadar (Died) Rukiyabi Hussain Jamadar (Died) T/h L.Rs. Gundu and Ors. — CA/974/2026
Disposed: --Admitted/Allowed/Granted/Rule Absolute on 05th May 2026.
CNR: HCBM030026892026
e-Filing Number
15-01-2026
Filing Number
CA/2041/2026
Filing Date
19-Jan-2026
Registration No
CA/974/2026
Registration Date
23-Jan-2026
Judge
Hon'ble Shri Justice Shailesh P. Brahme
Coram
Hon'ble Shri Justice Shailesh P. Brahme
Bench Type
Single
Judicial Branch
Civil
Decision Date
05-May-2026
Nature of Disposal
--Admitted/Allowed/Granted/Rule Absolute
Last updated 14-Jun-2026
Petitioner(s)
-
1.The Executive Engineer, Patbandhare Project Majbutikaran Division, Omerga, Tq. Omerga, Dist. Osmana Satish Bappasaheb Parnere
Respondent(s)
-
1.Hussain Abdul Jamadar (Died) Rukiyabi Hussain Jamadar (Died) T/h L.Rs. Gundu and Ors.
Adv. AGP WAIVES FOR R/3 AND 4,ADV.S.N.PATNE FOR R/ 1 AND 2 1123
-
2.Meheboob So Hussain Jamadar
-
3.The State Of Maharashtra Through The Collector Osmanabad
-
4.The Sub Divisional Officer and Special Land Acquisition Officer Manjara Project Osmanabad
Case History
-
Case disposedDisposed
-
30-Jun-2026
For Orders
Hon'ble Shri Justice Shailesh P. Brahme
-
05-May-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
Case Summary: CA/974/2026 The High Court of Bombay (Aurangabad Bench) condoned delays of 648 and 1097 days in preferring appeals by the applicants. The court partly allowed civil applications for withdrawal of deposited amounts (Rs. 11,02,068/- and Rs. 13,82,587/-), permitting applicants to receive 75% with accrued interest upon furnishing undertaking to the Registrar (Judicial), while directing the remaining 25% be invested in a nationalized bank. This case analysis is maintained by casestatus.in based on publicly available court records.
-
05-May-2026
For Orders
Hon'ble Shri Justice Shailesh P. Brahme
-
21-Apr-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
-
21-Apr-2026
For Orders
Hon'ble Shri Justice Shailesh P. Brahme
-
27-Jan-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
-
27-Jan-2026
First hearing
Initial hearing scheduled
-
19-Jan-2026
Case filed
Registration No. CA/974/2026
Case Summary: CA/974/2026 The High Court of Bombay (Aurangabad Bench) condoned delays of 648 and 1097 days in preferring appeals by the applicants. The court partly allowed civil applications for withdrawal of deposited amounts (Rs. 11,02,068/- and Rs. 13,82,587/-), permitting applicants to receive 75% with accrued interest upon furnishing undertaking to the Registrar (Judicial), while directing the remaining 25% be invested in a nationalized bank. This case analysis is maintained by casestatus.in based on publicly available court records.