SHILPI CONSTRUCTIONS ENGINEERS AND CONTRACTORS THROUGH PROPRIETOR GADDIGAIAH R. KURUDIMATH(SWAMI) vs DIPALI BALAKRISHNA GOENKA Advocate - Economic Laws Practice — ARBP/27/2026

Case under Arbitration and Conciliation Act 1996 Section 15. Next hearing: 11th June 2026.

Next hearing 11-Jun-2026

CNR: HCBM020300572022

Filing Number

ARBP/30051/2022

Filing Date

20-Sep-2022

Registration No

ARBP/27/2026

Registration Date

21-Jan-2026

Judge

Hon'ble Shri Justice Somasekhar Sundaresan

Coram

Hon'ble Shri Justice Somasekhar Sundaresan

Bench Type

Single

Category

ARBITRATION ( 4 )

Sub-Category

OTHERS ( 99 )

Judicial Branch

Original

Last updated 05-May-2026

Acts & Sections

Arbitration and Conciliation Act 1996 Section 15

Petitioner(s)

  1. 1.SHILPI CONSTRUCTIONS ENGINEERS AND CONTRACTORS THROUGH PROPRIETOR GADDIGAIAH R. KURUDIMATH(SWAMI)

    Adv. Kmc Legal Venture

Respondent(s)

  1. 1.DIPALI BALAKRISHNA GOENKA Advocate - Economic Laws Practice

Case History

  1. 11-Jun-2026

    Next hearingPending

  2. 11-Jun-2026

    At 3.00 P.M.

    Hon'ble Shri Justice Somasekhar Sundaresan

  3. 29-Apr-2026

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

    The Bombay High Court adjourned the Arbitration Petition filed by Shilpi Constructions Engineers & Contractors against Dipali Balakrishna Goenka and others to June 11, 2026. The Court took on record the reply affidavit filed by the Respondent and granted the Petitioner liberty to file a Rejoinder before the next date of hearing. This case analysis is maintained by casestatus.in based on publicly available court records.

  4. 29-Apr-2026

    For Second Chance

    Hon'ble Shri Justice Somasekhar Sundaresan

  5. 08-Apr-2026

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

  6. 08-Apr-2026

    At 3.00 P.M.

    Hon'ble Shri Justice Somasekhar Sundaresan

  7. 01-Apr-2026

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

  8. 01-Apr-2026

    At 3.00 P.M.

    Hon'ble Shri Justice Somasekhar Sundaresan

  9. 11-Mar-2026

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

  10. 11-Mar-2026

    At 3.00 P.M.

    Hon'ble Shri Justice Somasekhar Sundaresan

  11. 13-Mar-2024

    Shri. S. B. Bhansali (Prothonotary Senior Master))View PDF

  12. 27-Feb-2024

    Shri. S. B. Bhansali (Prothonotary Senior Master))View PDF

  13. 27-Feb-2024

    First hearing

    Initial hearing scheduled

  14. 20-Sep-2022

    Case filed

    Registration No. ARBP/27/2026

casestatus.in Summary

The Bombay High Court adjourned the Arbitration Petition filed by Shilpi Constructions Engineers & Contractors against Dipali Balakrishna Goenka and others to June 11, 2026. The Court took on record the reply affidavit filed by the Respondent and granted the Petitioner liberty to file a Rejoinder before the next date of hearing. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts