ESTEP NAGAR CO-OPERATIVE HOUSING SOCIETY LTD. vs VASTU DARSHAN DEVELOPERS LLP — IA/7273/2025

Case under Code of Civil Procedure Section 1. Next hearing: 19th June 2026.

Next hearing 19-Jun-2026

CNR: HCBM020256482024

Filing Number

IA/25641/2024

Filing Date

14-Aug-2024

Registration No

IA/7273/2025

Registration Date

24-Nov-2025

Judge

Hon'ble Shri Justice Somasekhar Sundaresan

Coram

Hon'ble Shri Justice Somasekhar Sundaresan

Bench Type

Single

Category

SUITS ( 38 )

Judicial Branch

Original

Last updated 11-May-2026

Acts & Sections

Code of Civil Procedure Section 1

Petitioner(s)

  1. 1.ESTEP NAGAR CO-OPERATIVE HOUSING SOCIETY LTD.

    Adv. SL Partners

Respondent(s)

  1. 1.VASTU DARSHAN DEVELOPERS LLP

  2. 2.STAINSLAUS STEPHEN DSILVA

  3. 3.D.M ENTERPRISES

  4. 4.BMK ENTERPRISES

  5. 5.VINCENT DSILVA ALIASWILSON DSILVA

  6. 6.MUNICIPAL CORPORATION OF GREATER MUMBAI

  7. 7.THE ASSISTANT MUNICIPAL COMMISSIONER

  8. 8.THE EXECUTIVE ENGINEER (BUILDING PROPOSAL)

  9. 9.THE DEPUTY CHIEF ENGINEER (BUILDING PROPOSAL)

Case History

  1. 19-Jun-2026

    Next hearingPending

  2. 19-Jun-2026

    Interim Application

    Hon'ble Shri Justice Somasekhar Sundaresan

  3. 07-May-2026

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

    Summary: The High Court of Bombay adjourned three consolidated interim applications (Nos. 6206, 7273, and 6780 of 2025) in Suit 291 of 2024 between Estep Nagar Co-operative Housing Society Ltd (petitioner) and Vastu Darshan Developers LLP (respondent) to 19th June 2026. The court ordered that all ad-interim or interim reliefs currently operative shall continue until the next hearing date, with non-time-limited reliefs remaining unaffected. This case analysis is maintained by casestatus.in based on publicly available court records.

  4. 07-May-2026

    Interim Application

    Hon'ble Shri Justice Somasekhar Sundaresan

  5. 18-Apr-2026

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

  6. 18-Apr-2026

    Production At 3.00 P.M.

    Hon'ble Shri Justice Somasekhar Sundaresan

  7. 15-Apr-2026

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

  8. 09-Apr-2026

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

  9. 09-Apr-2026

    Interim Application

    Hon'ble Shri Justice Somasekhar Sundaresan

  10. 13-Mar-2026

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

  11. 13-Mar-2026

    Interim Application

    Hon'ble Shri Justice Somasekhar Sundaresan

  12. 13-Feb-2026

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

  13. 13-Feb-2026

    Interim Application

    Hon'ble Shri Justice Somasekhar Sundaresan

  14. 28-Jan-2026

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

  15. 28-Jan-2026

    Interim Application

    Hon'ble Shri Justice Somasekhar Sundaresan

  16. 23-Dec-2025

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

  17. 23-Dec-2025

    Interim Application

    Hon'ble Shri Justice Somasekhar Sundaresan

  18. 03-Oct-2025

    Hon'ble Shri Justice Jitendra Shantilal JainView PDF

  19. 17-Sep-2025

    Interim Application

    Hon'ble Shri Justice R. I. Chagla

  20. 13-Aug-2025

    Hon'ble Shri Justice R. I. ChaglaView PDF

  21. 13-Aug-2025

    Interim Application

    Hon'ble Shri Justice R. I. Chagla

  22. 17-Jul-2025

    Hon'ble Shri Justice R. I. ChaglaView PDF

  23. 17-Jul-2025

    Due Matters - Adjourned OS

    Hon'ble Shri Justice R. I. Chagla

  24. 04-Jul-2025

    Hon'ble Shri Justice R. I. ChaglaView PDF

  25. 05-May-2025

    For Circulation

    Hon'ble Justice Shri Arif S. Doctor

  26. 24-Mar-2025

    Hon'ble Justice Shri Arif S. DoctorView PDF

  27. 21-Oct-2024

    Hon'ble Justice Shri Arif S. DoctorView PDF

  28. 30-Sep-2024

    Hon'ble Justice Shri Arif S. DoctorView PDF

  29. 30-Sep-2024

    First hearing

    Initial hearing scheduled

  30. 14-Aug-2024

    Case filed

    Registration No. IA/7273/2025

casestatus.in Summary

Summary: The High Court of Bombay adjourned three consolidated interim applications (Nos. 6206, 7273, and 6780 of 2025) in Suit 291 of 2024 between Estep Nagar Co-operative Housing Society Ltd (petitioner) and Vastu Darshan Developers LLP (respondent) to 19th June 2026. The court ordered that all ad-interim or interim reliefs currently operative shall continue until the next hearing date, with non-time-limited reliefs remaining unaffected. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts