MUKESH RAMANLAL GOKAL, AND 2 ORS. vs ASHOK JAGIJIVAN GOKAL, AND 4 ORS. Advocate - Chitnis and Company 1. — S/28/2014
Case under Code of Civil Procedure. Next hearing: 30th April 2026.
CNR: HCBM020250102013
Filing Number
S/1098/2013
Filing Date
11-Dec-2013
Registration No
S/28/2014
Registration Date
13-Jan-2014
Judge
Hon'ble Shri Justice Abhay Ahuja
Coram
Hon'ble Shri Justice Abhay Ahuja
Bench Type
Single
Category
SUITS ( 38 )
Judicial Branch
Original
Last updated 06-Apr-2026
Acts & Sections
Petitioner(s)
-
1.MUKESH RAMANLAL GOKAL, AND 2 ORS.
Adv. JHANGIANI NARULA and ASSOCIATES
-
2.BHARAT RAMANLAL GOKAL,
-
3.MERCANTILE CORPORATION,
Respondent(s)
-
1.ASHOK JAGIJIVAN GOKAL, AND 4 ORS. Advocate - Chitnis and Company 1.
-
2.CHETAN ASHOK GOKAL
-
3.HARSH ASHOK GOKAL,
-
4.SUDHA ASHOK GOKAL,
-
5.ASTOR CORPORATION PVT. LTD.,
-
6.KISHORE JAGIJIVAN GOKAL,
Case History
-
30-Apr-2026
Next hearingPending
-
30-Apr-2026
Due Matters - Adjourned OS
Hon'ble Shri Justice Abhay Ahuja
-
24-Mar-2026
Hon'ble Shri Justice Abhay AhujaView PDF
Summary In Interim Application No. 8132 of 2025, the Bombay High Court directed that repair work on the dangerous ground floor bathroom and toilet block in Mercantile House be completed by the appointed contractor no later than 30th April 2026, with the applicants bearing repair costs while reserving their right to seek reimbursement from respondents. The case was adjourned to 30th April 2026 for further hearing, and parties were directed to frame common draft issues for the connected suits. This case analysis is maintained by casestatus.in based on publicly available court records.
-
24-Mar-2026
Specially Assigned Matters
Hon'ble Shri Justice Abhay Ahuja
-
17-Feb-2026
Hon'ble Shri Justice Abhay AhujaView PDF
-
17-Feb-2026
For Framing Issues
Hon'ble Shri Justice Abhay Ahuja
-
13-Jan-2026
Hon'ble Shri Justice Abhay AhujaView PDF
-
13-Jan-2026
For Framing Issues
Hon'ble Shri Justice Abhay Ahuja
-
15-Dec-2025
Hon'ble Shri Justice Abhay AhujaView PDF
- 08-Dec-2014
-
08-Dec-2014
For Written Statement
Registrar(os)/Prothonotary and Sr. Master
-
13-Oct-2014
Registrar(os)/Prothonotary and Sr. MasterView PDF
-
13-Oct-2014
For Written Statement
Registrar(os)/Prothonotary and Sr. Master
-
23-Sep-2014
Addl.registrar(os)/Addl. Protho. and Sr. MasterView PDF
-
16-Jul-2014
Registrar(os)/Prothonotary and Sr. MasterView PDF
-
16-Jul-2014
First hearing
Initial hearing scheduled
-
11-Dec-2013
Case filed
Registration No. S/28/2014
Summary In Interim Application No. 8132 of 2025, the Bombay High Court directed that repair work on the dangerous ground floor bathroom and toilet block in Mercantile House be completed by the appointed contractor no later than 30th April 2026, with the applicants bearing repair costs while reserving their right to seek reimbursement from respondents. The case was adjourned to 30th April 2026 for further hearing, and parties were directed to frame common draft issues for the connected suits. This case analysis is maintained by casestatus.in based on publicly available court records.
Explore other courts