BUILDTECH ASSOCIATE vs MIDAS DEVELOPERS PRIVATE LIMITED AND 6 ORS AND SURESH NAMDEV MULIK AND 3 ORS (APPLICANT/INTERVENOR) Advocate - V S Jagdale, ,V S Jagdale,APPLICANT/INTERVENOR — CHSCD/1008/2019
Case under Code of Civil Procedure. Disposed: Contested--DISPOSED OFF on 07th May 2026.
CNR: HCBM020213352019
Filing Number
CHSCD/1124/2019
Filing Date
26-Aug-2019
Registration No
CHSCD/1008/2019
Registration Date
29-Aug-2019
Judge
Hon'ble Shri Justice Jitendra Shantilal Jain
Coram
Hon'ble Shri Justice Jitendra Shantilal Jain
Bench Type
Single
Category
SUITS ( 38 )
Judicial Branch
Original
Decision Date
07-May-2026
Nature of Disposal
Contested--DISPOSED OFF
Last updated 21-Jun-2026
Acts & Sections
Petitioner(s)
-
1.BUILDTECH ASSOCIATE
Respondent(s)
-
1.MIDAS DEVELOPERS PRIVATE LIMITED AND 6 ORS AND SURESH NAMDEV MULIK AND 3 ORS (APPLICANT/INTERVENOR) Advocate - V S Jagdale, ,V S Jagdale,APPLICANT/INTERVENOR
-
2.EDWYN JERRY D'MELLO
-
3.LILY D'MELLO JERRY
-
4.JERRY ALEX D'MELLO
-
5.TREZA, ALEX D'MELLO
-
6.NEHRU NAGAR SURBHI CO-OPERATIVE HOUSING SOCIETY LIMITED
-
7.ABHYUDAYA CO-OPERATIVE BANK LIMITED
Case History
-
Case disposedDisposed
-
07-May-2026
Hon'ble Shri Justice Jitendra Shantilal JainView PDF
The Bombay High Court disposed of Commercial Suit No. 189 of 2017 by consent settlement between Buildtech Associate and Midas Developers Pvt. Ltd. on May 7, 2026. The court granted leave to implead additional defendants, approved consent terms as court undertakings, and directed the bank (Defendant No. 7) to execute and register a re-conveyance deed for mortgaged property within eight weeks. All pending proceedings, including the counter-claim and contempt petition, were accordingly disposed of. This case analysis is maintained by casestatus.in based on publicly available court records.
-
16-Jun-2025
Hon'ble Justice Kamal KhataView PDF
-
10-Mar-2025
Hon'ble Shri Justice Abhay AhujaView PDF
-
10-Sep-2024
Hon'ble Justice Shri Arif S. DoctorView PDF
-
30-Jul-2024
Hon'ble Justice Shri Arif S. DoctorView PDF
-
26-Aug-2019
Case filed
Registration No. CHSCD/1008/2019
The Bombay High Court disposed of Commercial Suit No. 189 of 2017 by consent settlement between Buildtech Associate and Midas Developers Pvt. Ltd. on May 7, 2026. The court granted leave to implead additional defendants, approved consent terms as court undertakings, and directed the bank (Defendant No. 7) to execute and register a re-conveyance deed for mortgaged property within eight weeks. All pending proceedings, including the counter-claim and contempt petition, were accordingly disposed of. This case analysis is maintained by casestatus.in based on publicly available court records.