BUILDTECH ASSOCIATE vs MIDAS DEVELOPERS PRIVATE LIMITED AND 6 ORS AND SURESH NAMDEV MULIK AND 3 ORS (APPLICANT/INTERVENOR) Advocate - V S Jagdale, ,V S Jagdale,APPLICANT/INTERVENOR — CHSCD/1008/2019

Case under Code of Civil Procedure. Disposed: Contested--DISPOSED OFF on 07th May 2026.

Case disposed

CNR: HCBM020213352019

Filing Number

CHSCD/1124/2019

Filing Date

26-Aug-2019

Registration No

CHSCD/1008/2019

Registration Date

29-Aug-2019

Judge

Hon'ble Shri Justice Jitendra Shantilal Jain

Coram

Hon'ble Shri Justice Jitendra Shantilal Jain

Bench Type

Single

Category

SUITS ( 38 )

Judicial Branch

Original

Decision Date

07-May-2026

Nature of Disposal

Contested--DISPOSED OFF

Last updated 21-Jun-2026

Acts & Sections

Code of Civil Procedure

Petitioner(s)

  1. 1.BUILDTECH ASSOCIATE

Respondent(s)

  1. 1.MIDAS DEVELOPERS PRIVATE LIMITED AND 6 ORS AND SURESH NAMDEV MULIK AND 3 ORS (APPLICANT/INTERVENOR) Advocate - V S Jagdale, ,V S Jagdale,APPLICANT/INTERVENOR

  2. 2.EDWYN JERRY D'MELLO

  3. 3.LILY D'MELLO JERRY

  4. 4.JERRY ALEX D'MELLO

  5. 5.TREZA, ALEX D'MELLO

  6. 6.NEHRU NAGAR SURBHI CO-OPERATIVE HOUSING SOCIETY LIMITED

  7. 7.ABHYUDAYA CO-OPERATIVE BANK LIMITED

Case History

  1. Case disposedDisposed

  2. 07-May-2026

    Hon'ble Shri Justice Jitendra Shantilal JainView PDF

    The Bombay High Court disposed of Commercial Suit No. 189 of 2017 by consent settlement between Buildtech Associate and Midas Developers Pvt. Ltd. on May 7, 2026. The court granted leave to implead additional defendants, approved consent terms as court undertakings, and directed the bank (Defendant No. 7) to execute and register a re-conveyance deed for mortgaged property within eight weeks. All pending proceedings, including the counter-claim and contempt petition, were accordingly disposed of. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 16-Jun-2025

    Hon'ble Justice Kamal KhataView PDF

  4. 10-Mar-2025

    Hon'ble Shri Justice Abhay AhujaView PDF

  5. 10-Sep-2024

    Hon'ble Justice Shri Arif S. DoctorView PDF

  6. 30-Jul-2024

    Hon'ble Justice Shri Arif S. DoctorView PDF

  7. 26-Aug-2019

    Case filed

    Registration No. CHSCD/1008/2019

casestatus.in Summary

The Bombay High Court disposed of Commercial Suit No. 189 of 2017 by consent settlement between Buildtech Associate and Midas Developers Pvt. Ltd. on May 7, 2026. The court granted leave to implead additional defendants, approved consent terms as court undertakings, and directed the bank (Defendant No. 7) to execute and register a re-conveyance deed for mortgaged property within eight weeks. All pending proceedings, including the counter-claim and contempt petition, were accordingly disposed of. This case analysis is maintained by casestatus.in based on publicly available court records.