ROADWAY SOLUTIONS INDIA PVT LIMITED vs ICICI LOMBARD GENERAL INSURANCE CO LTD — CARBP/613/2026
Case under Arbitration and Conciliation Act 1996 Section 29A. Disposed: Contested--DISPOSED OFF on 07th May 2026.
CNR: HCBM020163742026
e-Filing Number
04-05-2026
Filing Number
CARBP/16374/2026
Filing Date
05-May-2026
Registration No
CARBP/613/2026
Registration Date
10-Jun-2026
Judge
Hon'ble Shri Justice Somasekhar Sundaresan
Coram
Hon'ble Shri Justice Somasekhar Sundaresan
Bench Type
Single
Category
ARBITRATION ( 4 )
Sub-Category
Extension of Arbitral Mandate ( 103 )
Judicial Branch
Original
Decision Date
07-May-2026
Nature of Disposal
Contested--DISPOSED OFF
Last updated 21-Jun-2026
Acts & Sections
Petitioner(s)
-
1.ROADWAY SOLUTIONS INDIA PVT LIMITED
Adv. Hussain Dholkawala
-
2.ROADWAY SOLUTIONS LONAVALA HIGHWAY PROJECT PVT LTD
Adv. DHOLKAWALA HUSSAIN ISHAK
-
3.ROADWAY SOLUTIONS NARAYANPUR HIGHWAY PROJECT PVT LTD
Adv. DHOLKAWALA HUSSAIN ISHAK
-
4.ROADWAY SOLUTIONS HINJEWADI HICHWAY PROJECT PVT LTD
Adv. DHOLKAWALA HUSSAIN ISHAK
-
5.ROADWAY SOLUTIONS MAHABALESHWAR HICHWAY PROJECT PVT LTD
Adv. DHOLKAWALA HUSSAIN ISHAK
Respondent(s)
-
1.ICICI LOMBARD GENERAL INSURANCE CO LTD
Case History
-
Case disposedDisposed
-
07-May-2026
Hon'ble Shri Justice Somasekhar SundaresanView PDF
The Bombay High Court granted Roadway Solutions India Pvt Limited's petition under Section 29-A of the Arbitration and Conciliation Act, 1996, extending the Arbitral Tribunal's mandate by three months until August 31, 2026. The court approved the joint request of both parties, noting that only the passing of the Arbitral Award remained pending. This case analysis is maintained by casestatus.in based on publicly available court records.
-
07-May-2026
Section 29 A
Hon'ble Shri Justice Somasekhar Sundaresan
-
05-May-2026
Case filed
Registration No. CARBP/613/2026
The Bombay High Court granted Roadway Solutions India Pvt Limited's petition under Section 29-A of the Arbitration and Conciliation Act, 1996, extending the Arbitral Tribunal's mandate by three months until August 31, 2026. The court approved the joint request of both parties, noting that only the passing of the Arbitral Award remained pending. This case analysis is maintained by casestatus.in based on publicly available court records.