MILIND MOHAN ATAKALE DEPUTY ENGINEER vs THE STATE OF MAHARASHTRA THRU THE CHIEF SECRETARY — HCBM20151982026
Case under Mah. Housing & Area Devolopment Act Section 1. Next hearing: 15th June 2026.
CNR: HCBM020151982026
Filing Number
IA/15381/2026
Filing Date
28-Apr-2026
Judge
Hon'ble Shri Justice G. S. Kulkarni , Hon'ble Ms Justice Aarti A. Sathe
Coram
Hon'ble Shri Justice G. S. Kulkarni , Hon'ble Ms Justice Aarti A. Sathe
Bench Type
Division
Judicial Branch
Original
Last updated 21-Jun-2026
Acts & Sections
Petitioner(s)
-
1.MILIND MOHAN ATAKALE DEPUTY ENGINEER
Adv. Manish Kelkar,Manish Kelkar,Manish Kelkar, ,Manish Kelkar
-
2.DHIRAJKUMAR NAVNITLAL JAIN DEPUTY ENGINEER
Adv. Manish Kelkar
-
3.ATUL ANANDRAO DESAI DEPUTY ENGINEER
Adv. Manish Kelkar
-
4.SANJAY NARAYANRAO YEREKAR DEPUTY ENGINEER
Adv. Manish Kelkar
-
5.PANKAJ NILKANTH PATIL DEPUTY ENGINEER
Adv. Manish Kelkar
-
6.PRAMOD KRISHNA SHINDE DEPUTY ENGINEER
Adv. Manish Kelkar
Respondent(s)
-
1.THE STATE OF MAHARASHTRA THRU THE CHIEF SECRETARY
-
2.ADDITIONAL CHIEF SECRETARY, HOUSING GOVERNMENT OF MAHARASHTRA
-
3.ADDITIONAL CHIEF SECRETARY, GENERAL ADMINISRATION DEPARTMENT, GOVT OF MAHARASHTRA
-
4.VICE PRESIDENT AND CHIEF EXECUTIVE OFFICER, MUMBAI HOUSING AND AREA DEVELOPMENT AUTHORITY (MHADA)
-
5.SECRETARY, MUMBAI HOUSING AND AREA DEVELOPMENT AUTHORITY (MHADA)
-
6.PIYUSH ARUN KAMBLE, DEPUTY ENGINEER (CIVIL)
-
7.MAYUR RAMDAS SONKUSARE, DEPUTY ENGINEER (CIVIL)
-
8.BHUSHAN POPAT KOLHE, DEPUTY ENGINEER,
-
9.PRADIP BANSILAL PHULPAGARE , DEPUTY ENGINEER (ORIG PETITIONER)
-
10.SUNIL NARENDRA DUDHALE DEPUTY ENGINEER VIGILANCE AND QUALITY CONTROL CELL, MHADA (ORG. PLAINTIFF)
-
11.ARCHANA MILAN BHOSALE CHIEF OFFICER, MUMBAI BOARD MHADA (ORG. PLAINTIFF)
-
12.APURVA NILESH CHAVAN DEPUTY ENGINEER, MUMBAI BOARD MHADA (ORIG PLAINTIFF)
-
13.SWAPNIL S. PATIL DEPUTY ENGINEER, MUMBAI BUILDING REPAIRS AND RECONSTRUCTION BOARD (ORIG PLAINTIFF)
-
14.MILIND TRYAMBAK BORODE, DEPUTY ENGINEER, BUILDING PERMISSION CELL MHADA (ORIG PLAINTIFF)
-
15.SACHIN BHAUSAHEB KHADTARE MUMBAI BUILDING REPAIRS AND RECONSTRUCTION BOARD (ORIG PLAINTIFF)
-
16.UTTAM S. GAIKWAD DEPUTY ENGINEER, MUMBAI BOARD, MHADA (ORIG PLAINTIFF)
-
17.SANJIV R.CHAVAN DEPUTY ENGINEER, MUMBAI BOARD, MHADA, (ORIG PLAINTIFF)
-
18.AMOL SURESHRAO BUDHKONDWAR DEPUTY ENGINEER, BUILDING PERMISSION CELL MHADA (ORIG PLAINTIFF)
-
19.UMESH REJENDRA WANKHEDE PRESIDENT, MAHARASHTRA GRIHNIRMAN KARMACHAR SANGHTANA MHADA (ORIG PLAINTIFF)
Case History
-
15-Jun-2026
Next hearingPending
-
15-Jun-2026
For Circulation
Hon'ble Shri Justice G. S. Kulkarni , Hon'ble Ms Justice Aarti A. Sathe
-
07-May-2026
Hon'ble Shri Justice G. S. Kulkarni,hon'ble Ms Justice Aarti A. SatheView PDF
Case Summary The Bombay High Court adjourned proceedings to 15 June 2026 while maintaining the ad-interim status-quo order dated 20 April 2026. The court restrained MHADA from undertaking any promotion exercise and directed MHADA to file an affidavit responding to the State Government's communication. Reply affidavits to the review petitions must be filed before the next hearing date. This case analysis is maintained by casestatus.in based on publicly available court records.
-
07-May-2026
First hearing
Initial hearing scheduled
-
28-Apr-2026
Case filed
Case Summary The Bombay High Court adjourned proceedings to 15 June 2026 while maintaining the ad-interim status-quo order dated 20 April 2026. The court restrained MHADA from undertaking any promotion exercise and directed MHADA to file an affidavit responding to the State Government's communication. Reply affidavits to the review petitions must be filed before the next hearing date. This case analysis is maintained by casestatus.in based on publicly available court records.