Wadhwa Estates and Developers India Pvt Ltd SL PARTNERS vs Moon Craft Apartments CHSL — HCBM20134242026

Case under Arbitration and Conciliation Act 1996 Section Section 9. Disposed: DISPOSED OFF on 18th June 2026.

Case disposed

CNR: HCBM020134242026

e-Filing Number

16-04-2026

Filing Number

CARBP/13424/2026

Filing Date

16-Apr-2026

Judge

Hon'ble Shri Justice Amit Borkar

Coram

Hon'ble Shri Justice Amit Borkar

Bench Type

Single

Category

ARBITRATION ( 4 )

Sub-Category

Interim Relief ( 102 )

Judicial Branch

Original

Decision Date

18-Jun-2026

Nature of Disposal

DISPOSED OFF

Last updated 21-Jun-2026

Acts & Sections

Arbitration and Conciliation Act 1996 Section Section 9

Petitioner(s)

  1. 1.Wadhwa Estates and Developers India Pvt Ltd SL PARTNERS

Respondent(s)

  1. 1.Moon Craft Apartments CHSL

  2. 2.Sajida Ul Haq

  3. 3.Muthar Shaikh

    Adv. Altaf Khan

  4. 4.Maryann Ratus

    Adv. Shubham B. Choudhar

  5. 5.Sofia Shaikh

    Adv. Shubham B. Choudhar

  6. 6.Imtiaz Ahmed

  7. 7.Seema Ashok

  8. 8.Afzal Ahmed

  9. 9.Sabeena Ahmed

  10. 10.Imtiaz Ahmed

  11. 11.Sabeena Ahmed

Case History

  1. Case disposedDisposed

  2. 18-Jun-2026

    Hon'ble Shri Justice Amit BorkarView PDF

    Summary: Wadhwa Estates v. Moon Craft Apartments CHSL Court Decision: The Bombay High Court partially allowed the petition, granting limited interim relief while rejecting requests for immediate eviction. Key Ruling: Dissenting members must execute "Consenting Member Declarations" within four weeks and are restrained from transferring or encumbering their flats. However, orders for actual vacation of premises and appointment of a Court Receiver were rejected as premature, as the contractual stage requiring such relief has not yet been reached under the Development Agreement. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 11-Jun-2026

    Hon'ble Shri Justice Amit BorkarView PDF

  4. 10-Jun-2026

    Hon'ble Shri Justice Amit BorkarView PDF

  5. 09-Jun-2026

    Arbp-For Hearing And Final Disposal U/S 9

    Hon'ble Shri Justice Sandeep V. Marne

  6. 07-May-2026

    Hon'ble Shri Justice Sandeep V. MarneView PDF

  7. 07-May-2026

    At 5.00 Pm

    Hon'ble Shri Justice Sandeep V. Marne

  8. 05-May-2026

    Hon'ble Shri Justice Sandeep V. MarneView PDF

  9. 05-May-2026

    First hearing

    Initial hearing scheduled

  10. 22-Apr-2026

    Hon'ble Shri Justice Sandeep V. MarneView PDF

  11. 16-Apr-2026

    Case filed

casestatus.in Summary

Summary: Wadhwa Estates v. Moon Craft Apartments CHSL Court Decision: The Bombay High Court partially allowed the petition, granting limited interim relief while rejecting requests for immediate eviction. Key Ruling: Dissenting members must execute "Consenting Member Declarations" within four weeks and are restrained from transferring or encumbering their flats. However, orders for actual vacation of premises and appointment of a Court Receiver were rejected as premature, as the contractual stage requiring such relief has not yet been reached under the Development Agreement. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts