NEELYOG BUILDERS PVT. LIMITED vs STATE OF MAHARASHTRA THROUGH THE PRINCIPAL SECRETARY, URBAN DEVELOPMENT DEPT Advocate - GP OS — WP/2638/2026

Case under Mah. Regional Town Planning Act Section 226. Next hearing: 01st July 2026.

Next hearing 01-Jul-2026

CNR: HCBM020130672026

Filing Number

WP/13067/2026

Filing Date

15-Apr-2026

Registration No

WP/2638/2026

Registration Date

03-Jun-2026

Judge

Hon'ble The Acting Chief Justice , Hon'ble Shri Justice Gautam A. Ankhad

Coram

Hon'ble The Acting Chief Justice , Hon'ble Shri Justice Gautam A. Ankhad

Bench Type

Division

Category

TOWN PLANNING ( 39 )

Sub-Category

SLUM REDEVELOPEMENT SCHEMES ( 3 )

Judicial Branch

Original

Last updated 14-Jun-2026

Acts & Sections

Mah. Regional Town Planning Act Section 226

Petitioner(s)

  1. 1.NEELYOG BUILDERS PVT. LIMITED

    Adv. MDP LEGAL

Respondent(s)

  1. 1.STATE OF MAHARASHTRA THROUGH THE PRINCIPAL SECRETARY, URBAN DEVELOPMENT DEPT Advocate - GP OS

  2. 2.SLUM REHABILITATION AUTHORITY BRIHANMUMBAI THROUGH THE CHIEF EXECUTIVE OFFICER

  3. 3.BRIHANMUMBAI MUNICIPAL CORPORATION THROUGH THE MUNICIPAL COMMISSIONER

  4. 4.CHIEF ENGINEER (DEVELOPMENT PLAN)

Case History

  1. 01-Jul-2026

    Next hearingPending

  2. 01-Jul-2026

    Fresh Admission

    Hon'ble The Acting Chief Justice , Hon'ble Shri Justice Gautam A. Ankhad

  3. 12-Jun-2026

    Hon'ble Shri Justice M. S. Karnik,hon'ble Shri Justice S. M. ModakView PDF

  4. 12-Jun-2026

    First hearing

    Initial hearing scheduled

  5. 10-Jun-2026

    Hon'ble The Acting Chief Justice,hon'ble Shri Justice Gautam A. AnkhadView PDF

    Case Summary: WP/2638/2026 The case involving Neelyog Builders Pvt. Limited against the State of Maharashtra and others was adjourned. The court issued a common order on 10th June 2026 directing removal of office objections within two weeks, filing of affidavits in reply at least one week before the next date, and completion of service of notice on respondents. The case was rescheduled for listing on 9th July 2026 at 3:00 p.m., with interim orders continuing subject to compliance with procedural requirements. This case analysis is maintained by casestatus.in based on publicly available court records.

  6. 15-Apr-2026

    Case filed

    Registration No. WP/2638/2026

casestatus.in Summary

Case Summary: WP/2638/2026 The case involving Neelyog Builders Pvt. Limited against the State of Maharashtra and others was adjourned. The court issued a common order on 10th June 2026 directing removal of office objections within two weeks, filing of affidavits in reply at least one week before the next date, and completion of service of notice on respondents. The case was rescheduled for listing on 9th July 2026 at 3:00 p.m., with interim orders continuing subject to compliance with procedural requirements. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts

Search Another Case