JYOTI BUILDERS A PARTNERSHIP FIRM vs STATE OF MAHARASHTRA REVENUE AND FOREST DEPARTMENT Advocate - GP OS, ,GP OS,GP OS,GP OS,RAVLEEN SABHARWAL,RAVLEEN SABHARWAL — WP/2123/2025
Case under Mah. Slum Areas Act Section 226. Next hearing: 11th June 2026.
CNR: HCBM020109032025
Filing Number
WP/10903/2025
Filing Date
04-Apr-2025
Registration No
WP/2123/2025
Registration Date
18-Jun-2025
Judge
Hon'ble Shri Justice M. S. Karnik , Hon'ble Shri Justice S. M. Modak
Coram
Hon'ble Shri Justice M. S. Karnik , Hon'ble Shri Justice S. M. Modak
Bench Type
Division
Category
SLUM AREAS ( 49 )
Sub-Category
Slum areas ( 1 )
Judicial Branch
Original
Last updated 29-May-2026
Acts & Sections
Petitioner(s)
-
1.JYOTI BUILDERS A PARTNERSHIP FIRM
Adv. Yogesh Adhia
Respondent(s)
-
1.STATE OF MAHARASHTRA REVENUE AND FOREST DEPARTMENT Advocate - GP OS, ,GP OS,GP OS,GP OS,RAVLEEN SABHARWAL,RAVLEEN SABHARWAL
-
2.THE COLLECTOR MUMBAI SUBURBAN DISTRICT
Adv. GP OS
-
3.THE CHIEF EXECUTIVE OFFICER SLUM REHABILITATION AUTHORITY
Adv. RAVLEEN SABHARWAL
-
4.THE EXECUTIVE ENGINEER-P/S SLUM REHABILITATION AUTHORITY
Adv. RAVLEEN SABHARWAL
-
5.THE INSPECTOR GENERAL OF REGISTRTION AND CONTROLLER OF STAMPS
Adv. GP OS
-
6.LAXMIBAI MANGAL PAGE
Adv. Hemant Ghadigaonkar
Case History
-
11-Jun-2026
Next hearingPending
-
11-Jun-2026
For Admission
Hon'ble Shri Justice M. S. Karnik , Hon'ble Shri Justice S. M. Modak
-
23-Apr-2026
Hon'ble Shri Justice M. S. Karnik,hon'ble Shri Justice S. M. ModakView PDF
Case Summary: WP 2123/2025 - Jyoti Builders v. State of Maharashtra The Bombay High Court adjourned the writ petition filed by Jyoti Builders (a partnership firm) against the State of Maharashtra Revenue and Forest Department and other respondents. The court granted Respondent No. 4's request for two weeks to file an affidavit-in-reply, with rejoinder to be filed within two weeks thereafter. The matter is listed for hearing on 11th June 2026, and the interim order previously granted on 2nd December 2025 continues till the next date. This case analysis is maintained by casestatus.in based on publicly available court records.
-
31-Jul-2025
For Circulation
Hon'ble Shri Justice G. S. Kulkarni , Hon'ble Justice Shri Arif S. Doctor
-
24-Jul-2025
Hon'ble Shri Justice G. S. Kulkarni,hon'ble Justice Shri Arif S. DoctorView PDF
-
09-Jul-2025
Fresh Admission
Hon'ble Shri Justice G. S. Kulkarni , Hon'ble Justice Shri Arif S. Doctor
-
02-Jul-2025
Hon'ble Shri Justice G. S. Kulkarni,hon'ble Justice Shri Arif S. DoctorView PDF
-
02-Jul-2025
Fresh Admission
Hon'ble Shri Justice G. S. Kulkarni , Hon'ble Justice Shri Arif S. Doctor
-
25-Jun-2025
Hon'ble Shri Justice G. S. Kulkarni,hon'ble Justice Shri Arif S. DoctorView PDF
-
25-Jun-2025
Fresh Admission
Hon'ble Shri Justice G. S. Kulkarni , Hon'ble Justice Shri Arif S. Doctor
-
09-May-2025
Hon'ble Justice Dr. Neela Kedar Gokhale,hon'ble Shri Justice A.S. ChandurkarView PDF
-
09-May-2025
For Circulation
Hon'ble Justice Dr. Neela Kedar Gokhale , Hon'ble Shri Justice A.S. Chandurkar
-
08-May-2025
Hon'ble Justice Dr. Neela Kedar Gokhale,hon'ble Shri Justice A.S. ChandurkarView PDF
-
08-May-2025
First hearing
Initial hearing scheduled
-
04-Apr-2025
Case filed
Registration No. WP/2123/2025
Case Summary: WP 2123/2025 - Jyoti Builders v. State of Maharashtra The Bombay High Court adjourned the writ petition filed by Jyoti Builders (a partnership firm) against the State of Maharashtra Revenue and Forest Department and other respondents. The court granted Respondent No. 4's request for two weeks to file an affidavit-in-reply, with rejoinder to be filed within two weeks thereafter. The matter is listed for hearing on 11th June 2026, and the interim order previously granted on 2nd December 2025 continues till the next date. This case analysis is maintained by casestatus.in based on publicly available court records.