Perfect Infraengineers Ltd vs The Board of Directors of Technology Development Board — HCBM20031412026
Case under Micro, Small & Medium Enterprise Dev. Act Section 9. Next hearing: 10th June 2026.
CNR: HCBM020031412026
e-Filing Number
29-01-2026
Filing Number
IA/3141/2026
Filing Date
29-Jan-2026
Judge
Hon'ble Shri Justice Abhay Ahuja
Coram
Hon'ble Shri Justice Abhay Ahuja
Bench Type
Single
Judicial Branch
Original
Last updated 19-Jun-2026
Acts & Sections
Petitioner(s)
-
1.Perfect Infraengineers Ltd
Adv. Adv Hemali Merva
-
2.Manisha Nimesh Mehta
Adv. KURNE HEMALI SURESH
-
3.Nimesh Mehta
Adv. KURNE HEMALI SURESH
Respondent(s)
-
1.The Board of Directors of Technology Development Board
-
2.The Project Monitoring Committee
-
3.Union of India
-
4.Rajesh Jain
-
5.The Board of directors Of ICICI Bank
-
6.Jignesh Shelani
-
7.Vijay Kumar
-
8.Sandeep Bakshi
-
9.Benoy Idiculla
-
10.Ministry of Micro Small and medium Enterprises
-
11.Ministry of Finance
-
12.State of Maharashtra
-
13.Reserve Bank of India
-
14.TransUnion CIBIL
-
15.Gaurang Chhotalal Shah
-
16.Jayalaxmi Neelkantan
-
17.P G Neelakantan
-
18.Prachi Vinit Deliwala
-
19.Equivas Capital Private Ltd
-
20.Sonal Sumit Mehta
-
21.Tvisha Corporate Advisors LLP
-
22.Standard Capital Market Limited
-
23.Alpana Sanjay Dangi
-
24.Ministry Of Corporate Affairs
-
25.Registrar of Companies
-
26.Bank Of India
-
27.National stock Exchange Of India Limited
-
28.The Chaiman
-
29.The Chairman
-
30.The Attorney General Of India
Case History
-
10-Jun-2026
Next hearingPending
-
08-Jul-2026
Due Matters - Adjourned OS
Hon'ble Shri Justice Abhay Ahuja
-
10-Jun-2026
Hon'ble Shri Justice Abhay AhujaView PDF
CASE SUMMARY: The High Court of Bombay dismissed the claim of urgency and transferred the matter to the regular bench. Perfect Infraengineers Ltd and others sought dispensation of leave under Section 80(2) CPC, but the court found no urgency after the parallel NCLT proceedings were adjourned to 21 July 2026. The court permitted defendant ICICI Bank to file replies and rejoinders, and scheduled the next hearing for 8 July 2026 before the regular bench. This case analysis is maintained by casestatus.in based on publicly available court records.
-
08-May-2026
Hon'ble Justice Shri Arif S. DoctorView PDF
-
08-Apr-2026
At 3.00 P.M.
Hon'ble Shri Justice Milind N. Jadhav
-
30-Mar-2026
Hon'ble Shri Justice Milind N. JadhavView PDF
-
30-Mar-2026
First On Board (Fob)
Hon'ble Shri Justice Milind N. Jadhav
-
23-Mar-2026
Hon'ble Shri Justice Milind N. JadhavView PDF
-
23-Mar-2026
First On Board (Fob)
Hon'ble Shri Justice Milind N. Jadhav
-
09-Mar-2026
Hon'ble Shri Justice Milind N. JadhavView PDF
-
09-Mar-2026
For Circulation
Hon'ble Shri Justice Milind N. Jadhav
-
04-Mar-2026
Hon'ble Shri Justice Milind N. JadhavView PDF
-
04-Mar-2026
For Circulation
Hon'ble Shri Justice Milind N. Jadhav
-
25-Feb-2026
Hon'ble Shri Justice Milind N. JadhavView PDF
-
25-Feb-2026
For Circulation
Hon'ble Shri Justice Milind N. Jadhav
-
25-Feb-2026
For Circulation
Hon'ble Shri Justice Milind N. Jadhav
-
18-Feb-2026
Hon'ble Shri Justice Milind N. JadhavView PDF
-
11-Feb-2026
Hon'ble Shri Justice Milind N. JadhavView PDF
-
11-Feb-2026
First hearing
Initial hearing scheduled
-
29-Jan-2026
Case filed
CASE SUMMARY: The High Court of Bombay dismissed the claim of urgency and transferred the matter to the regular bench. Perfect Infraengineers Ltd and others sought dispensation of leave under Section 80(2) CPC, but the court found no urgency after the parallel NCLT proceedings were adjourned to 21 July 2026. The court permitted defendant ICICI Bank to file replies and rejoinders, and scheduled the next hearing for 8 July 2026 before the regular bench. This case analysis is maintained by casestatus.in based on publicly available court records.