Sharma Constructions Company and Ors vs Anand Nagar Badal Co operative Housing Society Ltd and Ors — HCBM20023572026
Case under Arbitration and Conciliation Act 1996 Section 9. Next hearing: 10th June 2026.
CNR: HCBM020023572026
e-Filing Number
21-01-2026
Filing Number
ARBP/2357/2026
Filing Date
22-Jan-2026
Judge
Shri. A. H. Laddhad(Prothonotary Senior Master)
Coram
Shri. A. H. Laddhad(Prothonotary Senior Master)
Bench Type
Single
Category
ARBITRATION ( 4 )
Sub-Category
Interim Relief ( 102 )
Judicial Branch
Original
Last updated 10-May-2026
Acts & Sections
Petitioner(s)
-
1.Sharma Constructions Company and Ors
Adv. KUNAL CHHEDA
-
2.Vinod Sharma
Adv. CHHEDA KUNAL CHANDRAKANT
-
3.Chanda Sharma
Adv. CHHEDA KUNAL CHANDRAKANT
Respondent(s)
-
1.Anand Nagar Badal Co operative Housing Society Ltd and Ors
Adv. ,Mikdad Aziz Zummerwala,Mikdad Aziz Zummerwala,Mikdad Aziz Zummerwala 1123
-
2.Ramesh Prakash Mohan
Adv. ZUMMERWALA MIKDAD AZIZ
-
3.Sonia Kamal Kishore Malhotra
Adv. ZUMMERWALA MIKDAD AZIZ
-
4.Margret Miranda
-
5.Vasumathy Nair/ Maahi Raaza
Adv. ZUMMERWALA MIKDAD AZIZ
Case History
-
10-Jun-2026
Next hearingPending
-
10-Jun-2026
Arbp-For Hearing And Final Disposal U/S 9
Hon'ble Shri Justice Sandeep V. Marne
-
20-Apr-2026
Hon'ble Shri Justice Sandeep V. MarneView PDF
Summary: The Bombay High Court adjourned the arbitration petition filed by Sharma Constructions Company against Anand Nagar Badal Co Operative Housing Society Ltd to 10th June 2026 due to lack of time. Any interim or ad-interim relief currently operating shall continue until the next hearing date. This case analysis is maintained by casestatus.in based on publicly available court records.
-
20-Apr-2026
At 3.00 P.M.
Hon'ble Shri Justice Sandeep V. Marne
-
17-Apr-2026
Shri. A. H. Laddhad(Prothonotary Senior Master)View PDF
-
16-Apr-2026
Hon'ble Shri Justice Sandeep V. MarneView PDF
-
16-Apr-2026
For Circulation
Hon'ble Shri Justice Sandeep V. Marne
-
09-Apr-2026
Hon'ble Shri Justice Sandeep V. MarneView PDF
-
09-Apr-2026
For Circulation
Hon'ble Shri Justice Sandeep V. Marne
-
30-Mar-2026
Hon'ble Shri Justice Sandeep V. MarneView PDF
-
30-Mar-2026
Arbp-For Hearing And Final Disposal U/S 9
Hon'ble Shri Justice Sandeep V. Marne
-
16-Mar-2026
Hon'ble Shri Justice Sandeep V. MarneView PDF
-
16-Mar-2026
Arbp-For Hearing And Final Disposal U/S 9
Hon'ble Shri Justice Sandeep V. Marne
-
23-Feb-2026
Hon'ble Shri Justice Sandeep V. MarneView PDF
-
23-Feb-2026
First hearing
Initial hearing scheduled
-
04-Feb-2026
Hon'ble Shri Justice Sandeep V. MarneView PDF
-
22-Jan-2026
Case filed
Summary: The Bombay High Court adjourned the arbitration petition filed by Sharma Constructions Company against Anand Nagar Badal Co Operative Housing Society Ltd to 10th June 2026 due to lack of time. Any interim or ad-interim relief currently operating shall continue until the next hearing date. This case analysis is maintained by casestatus.in based on publicly available court records.
Explore other courts