Laxmi Narayan Bagad and Ors vs Apcon Construction Company — HCBM20019412026
Case under Arbitration and Conciliation Act 1996 Section 37. Next hearing: 07th April 2026.
CNR: HCBM020019412026
e-Filing Number
19-01-2026
Filing Number
ARBP/1941/2026
Filing Date
19-Jan-2026
Judge
Hon'ble Shri Justice Somasekhar Sundaresan
Coram
Hon'ble Shri Justice Somasekhar Sundaresan
Bench Type
Single
Category
ARBITRATION ( 4 )
Sub-Category
OTHERS ( 99 )
Judicial Branch
Original
Last updated 06-Apr-2026
Acts & Sections
Petitioner(s)
-
1.Laxmi Narayan Bagad and Ors
Adv. SACHIN V MASURKAR
-
2.Ganesh Manohar Shedge
Adv. MASURKAR SACHIN VASANT
-
3.Dharmendra Kumar Pandey
Adv. MASURKAR SACHIN VASANT
-
4.Phoolraji Pandey
Adv. MASURKAR SACHIN VASANT
-
5.Vilas Waman Mane
Adv. MASURKAR SACHIN VASANT
-
6.Aiesha Allaudin Patel
Adv. MASURKAR SACHIN VASANT
-
7.Alka B Dharpawar
Adv. MASURKAR SACHIN VASANT
-
8.Anil Manohar Shedge
Adv. MASURKAR SACHIN VASANT
-
9.Ramsahay B Gupta
Adv. MASURKAR SACHIN VASANT
-
10.Kavi Manohar Shedge
Adv. MASURKAR SACHIN VASANT
-
11.Sanjay Rajaram Kadam
Adv. MASURKAR SACHIN VASANT
Respondent(s)
-
1.Apcon Construction Company
-
2.Sujata Uday Rawool
-
3.Uday Rawool
-
4.Nehru Nagar Vishwadham CHS Ltd
Adv. Chetan C Agrawal
Case History
-
07-Apr-2026
Next hearingPending
-
02-Apr-2026
At 3.00 P.M.
Hon'ble Shri Justice Somasekhar Sundaresan
-
24-Mar-2026
Hon'ble Shri Justice Somasekhar SundaresanView PDF
The Arbitration Petition was adjourned for hearing on 02/04/2026 under Section 37 before the Bombay High Court. Justice Somasekhar Sundaresan presided over the matter between Laxmi Narayan Bagad (Petitioner) and Apcon Construction Company (Respondent). This case analysis is maintained by casestatus.in based on publicly available court records.
-
24-Mar-2026
Section 37 OS
Hon'ble Shri Justice Somasekhar Sundaresan
-
13-Mar-2026
Hon'ble Shri Justice Somasekhar SundaresanView PDF
-
13-Mar-2026
Section 37 OS
Hon'ble Shri Justice Somasekhar Sundaresan
-
06-Mar-2026
Hon'ble Shri Justice Somasekhar SundaresanView PDF
-
06-Mar-2026
Section 37 OS
Hon'ble Shri Justice Somasekhar Sundaresan
-
26-Feb-2026
Hon'ble Shri Justice Somasekhar SundaresanView PDF
-
26-Feb-2026
Case Management Hearing
Hon'ble Shri Justice Somasekhar Sundaresan
-
11-Feb-2026
Hon'ble Shri Justice Somasekhar SundaresanView PDF
-
11-Feb-2026
First hearing
Initial hearing scheduled
-
19-Jan-2026
Case filed
The Arbitration Petition was adjourned for hearing on 02/04/2026 under Section 37 before the Bombay High Court. Justice Somasekhar Sundaresan presided over the matter between Laxmi Narayan Bagad (Petitioner) and Apcon Construction Company (Respondent). This case analysis is maintained by casestatus.in based on publicly available court records.
Explore other courts