SAKTHI ENGINEERING WORKS vs VELARAM KANARAM PATEL AND ANR — WP/6608/2025

Case under Constitution of India Section 227. Next hearing: 07th May 2026.

Next hearing 07-May-2026

CNR: HCBM010592502025

Filing Number

WP/23047/2025

Filing Date

17-Nov-2025

Registration No

WP/6608/2025

Registration Date

05-Dec-2025

Judge

Hon'ble Shri Justice N. J. Jamadar

Coram

Hon'ble Shri Justice N. J. Jamadar

Bench Type

Single

Category

CRIMINAL ( 9 )

Sub-Category

Seeking Directions ( 105 )

Judicial Branch

Criminal

Last updated 13-Jun-2026

Acts & Sections

Constitution of India Section 227
Bharatiya Nagarik Suraksha Sanhita Section 528
Criminal Procedure Code (Cr.pc) Section 311
Negotiable Instruments Act, 1881 Section 138

Petitioner(s)

  1. 1.SAKTHI ENGINEERING WORKS

    Adv. Chandni Chawla

Respondent(s)

  1. 1.VELARAM KANARAM PATEL AND ANR

Case History

  1. 07-May-2026

    Next hearingPending

  2. 07-May-2026

    Hon'ble Shri Justice N. J. JamadarView PDF

    Case Summary: WP/6608/2025 - Sakthi Engineering Works v. Velaram Kanaram Patel and Anr The Bombay High Court adjourned the writ petition to 2nd July 2026. The court maintained the ad-interim relief previously granted in favor of petitioner Sakthi Engineering Works, which shall continue until the next hearing date. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 07-May-2026

    For Admission

    Hon'ble Shri Justice N. J. Jamadar

  4. 12-Mar-2026

    Hon'ble Shri Justice N. J. JamadarView PDF

  5. 12-Mar-2026

    Fresh Admission

    Hon'ble Shri Justice N. J. Jamadar

  6. 22-Jan-2026

    Hon'ble Shri Justice N. J. JamadarView PDF

  7. 15-Dec-2025

    Fresh Admission

    Hon'ble Shri Justice N. J. Jamadar

  8. 11-Dec-2025

    Hon'ble Shri Justice N. J. JamadarView PDF

  9. 11-Dec-2025

    First hearing

    Initial hearing scheduled

  10. 17-Nov-2025

    Case filed

    Registration No. WP/6608/2025

casestatus.in Summary

Case Summary: WP/6608/2025 - Sakthi Engineering Works v. Velaram Kanaram Patel and Anr The Bombay High Court adjourned the writ petition to 2nd July 2026. The court maintained the ad-interim relief previously granted in favor of petitioner Sakthi Engineering Works, which shall continue until the next hearing date. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts

Search Another Case