THE STATE OF MAHARASHTRA AND ANR GOVT PLEADER vs SMT. ANTIBAI YESHWANT JADHAV — CAF/2087/2015

Case under Land Acquisition Act. Disposed: Contested--Disposed Off on 17th April 2026.

Case disposed Next hearing 07-Jan-2016

CNR: HCBM010491652012

Filing Number

CAF/33587/2012

Filing Date

04-Dec-2012

Registration No

CAF/2087/2015

Registration Date

15-Jun-2015

Judge

Hon'ble Shri Justice Abhay Ahuja

Coram

Hon'ble Shri Justice Abhay Ahuja

Bench Type

Single

Category

ORDINARY CIVIL ( 30 )

Sub-Category

ORDINARY CIVIL ( 11 )

Judicial Branch

Civil

Decision Date

17-Apr-2026

Nature of Disposal

Contested--Disposed Off

Last updated 27-May-2026

Acts & Sections

Land Acquisition Act

Petitioner(s)

  1. 1.THE STATE OF MAHARASHTRA AND ANR GOVT PLEADER

  2. 2.THE EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION.

Respondent(s)

  1. 1.SMT. ANTIBAI YESHWANT JADHAV

Case History

  1. Case disposedDisposed

  2. 17-Apr-2026

    Hon'ble Shri Justice Abhay AhujaView PDF

    The High Court of Bombay allowed the State of Maharashtra to withdraw its appeal concerning land acquisition compensation for the Unnayi Irrigation Dam Project. The State's initial award of Rs. 3,959 was enhanced to Rs. 15,229 by the Reference Court—less than four times the original amount—permitting withdrawal under state policy notifications. The appeal was disposed as withdrawn with court fee refund. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 17-Apr-2026

    For Final Hearing

    Hon'ble Shri Justice Abhay Ahuja

  4. 30-Jan-2026

    Hon'ble Shri Justice Abhay AhujaView PDF

  5. 01-Oct-2020

    For Orders [Civil Side Matters]

    Hon'ble Shri Justice M. S. Karnik

  6. 09-Mar-2016

    Registrar(judicial II Fa)View PDF

  7. 09-Mar-2016

    For Orders

    Registrar(judicial II Fa)

  8. 07-Jan-2016

    First hearing

    Initial hearing scheduled

  9. 04-Dec-2012

    Case filed

    Registration No. CAF/2087/2015

casestatus.in Summary

The High Court of Bombay allowed the State of Maharashtra to withdraw its appeal concerning land acquisition compensation for the Unnayi Irrigation Dam Project. The State's initial award of Rs. 3,959 was enhanced to Rs. 15,229 by the Reference Court—less than four times the original amount—permitting withdrawal under state policy notifications. The appeal was disposed as withdrawn with court fee refund. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts

Search Another Case