MALHARI ISHWAR SHIVEKAR vs THE STATE OF MAHARASHTRA THR. SECRETARY REHABILITATION DEPARTMENT AND ORS — WP/14474/2025

Case under Project Affected Persons Rehabilitation Act Section NA. Next hearing: 19th June 2026.

Next hearing 19-Jun-2026

CNR: HCBM010439232025

Filing Number

WP/27819/2025

Filing Date

11-Aug-2025

Registration No

WP/14474/2025

Registration Date

28-Oct-2025

Judge

Hon'ble Shri Justice Manish Pitale , Hon'ble Shri Justice Shreeram Vinayak Shirsat

Coram

Hon'ble Shri Justice Manish Pitale , Hon'ble Shri Justice Shreeram Vinayak Shirsat

Bench Type

Division

Category

ORDINARY CIVIL ( 30 )

Sub-Category

Project Affected Persons ( 100 )

Judicial Branch

Civil

Last updated 13-Jun-2026

Acts & Sections

Project Affected Persons Rehabilitation Act Section NA

Petitioner(s)

  1. 1.MALHARI ISHWAR SHIVEKAR

    Adv. LENGARE Y B

Respondent(s)

  1. 1.THE STATE OF MAHARASHTRA THR. SECRETARY REHABILITATION DEPARTMENT AND ORS

  2. 2.THE COLLECTOR PUNE

  3. 3.ADDITIONAL COLLECTOR PUNE

  4. 4.THE DEPUTY COLLECTOR (RESETTLEMENT) PUNE

Case History

  1. 19-Jun-2026

    Next hearingPending

  2. 19-Jun-2026

    -For Directions

    Hon'ble Shri Justice A.S. Gadkari , Hon'ble Justice Kamal Khata

  3. 06-May-2026

    Hon'ble Shri Justice A.S. Gadkari,hon'ble Justice Kamal KhataView PDF

    The case WP/14474/2025 (Malhari Ishwar Shivekar v. State of Maharashtra) was heard together with five related petitions concerning rehabilitation of Project Affected Persons of the Bhama Askhed Project. The court found the state's affidavit statement regarding monetary compensation policy to be "palpably incorrect" as land allotments continued after June 17, 2025, contrary to the government's stated decision. The court issued notices to five beneficiaries of disputed land allotments, calling upon them to show cause why these allotments should not be cancelled for alleged violation of government policy and malpractices by rehabilitation officials, with returnable date set for June 19, 2026. This case analysis is maintained by casestatus.in based on publicly available court records.

  4. 06-May-2026

    Speaking To Minutes-

    Hon'ble Shri Justice A.S. Gadkari , Hon'ble Justice Kamal Khata

  5. 28-Apr-2026

    Hon'ble Shri Justice A.S. Gadkari,hon'ble Justice Kamal KhataView PDF

  6. 28-Apr-2026

    -Due Admission

    Hon'ble Shri Justice A.S. Gadkari , Hon'ble Justice Kamal Khata

  7. 09-Apr-2026

    Hon'ble Shri Justice A.S. Gadkari,hon'ble Justice Kamal KhataView PDF

  8. 09-Apr-2026

    -Due Admission

    Hon'ble Shri Justice A.S. Gadkari , Hon'ble Justice Kamal Khata

  9. 26-Mar-2026

    Hon'ble Shri Justice A.S. Gadkari,hon'ble Justice Kamal KhataView PDF

  10. 26-Mar-2026

    -Admission

    Hon'ble Shri Justice A.S. Gadkari , Hon'ble Justice Kamal Khata

  11. 05-Mar-2026

    Hon'ble Shri Justice A.S. Gadkari,hon'ble Justice Kamal KhataView PDF

  12. 05-Mar-2026

    First hearing

    Initial hearing scheduled

  13. 11-Aug-2025

    Case filed

    Registration No. WP/14474/2025

casestatus.in Summary

The case WP/14474/2025 (Malhari Ishwar Shivekar v. State of Maharashtra) was heard together with five related petitions concerning rehabilitation of Project Affected Persons of the Bhama Askhed Project. The court found the state's affidavit statement regarding monetary compensation policy to be "palpably incorrect" as land allotments continued after June 17, 2025, contrary to the government's stated decision. The court issued notices to five beneficiaries of disputed land allotments, calling upon them to show cause why these allotments should not be cancelled for alleged violation of government policy and malpractices by rehabilitation officials, with returnable date set for June 19, 2026. This case analysis is maintained by casestatus.in based on publicly available court records.