GARDEN SECURITIES AND PROPERTIES LL.P THR ITS KIRAN SHAH. vs MUNICIPAL CORPORATION FOR GRETER MUMBAI THR R/ CENTRAL WARD — IA/8391/2025

Case under Bombay Municipal Corporation Act Section 6. Disposed: --Disposed Off on 10th April 2026.

Case disposed

CNR: HCBM010288642025

Filing Number

IA/18407/2025

Filing Date

23-May-2025

Registration No

IA/8391/2025

Registration Date

27-May-2025

Judge

Hon'ble Shri Justice Milind N. Jadhav

Coram

Hon'ble Shri Justice Milind N. Jadhav

Bench Type

Single

Category

ELECTION ( 12 )

Sub-Category

MUNICIPAL CORPORATION ( 7 )

Judicial Branch

Civil

Decision Date

10-Apr-2026

Nature of Disposal

--Disposed Off

Last updated 22-Apr-2026

Acts & Sections

Bombay Municipal Corporation Act Section 6

Petitioner(s)

  1. 1.GARDEN SECURITIES AND PROPERTIES LL.P THR ITS KIRAN SHAH.

    Adv. Roma Chudasama

Respondent(s)

  1. 1.MUNICIPAL CORPORATION FOR GRETER MUMBAI THR R/ CENTRAL WARD

Case History

  1. Case disposedDisposed

  2. 10-Apr-2026

    Hon'ble Shri Justice Milind N. JadhavView PDF

    The Bombay High Court allowed the appeal and quashed the Municipal Corporation's notice and order for land acquisition, but on consent of both parties. The appellant agreed to surrender 3,127.43 sq.mtrs of land for a public road project connecting the Western Express Highway, with compensation payable under the Right to Fair Compensation and Transparency in Land Acquisition Act, 2013 instead of the Municipal Corporation Act. The State Government was directed to complete land acquisition proceedings within two months, and the Corporation may proceed with road construction pending acquisition completion. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 10-Apr-2026

    First On Board (Fob)

    Hon'ble Shri Justice Milind N. Jadhav

  4. 09-Apr-2026

    Hon'ble Shri Justice Milind N. JadhavView PDF

  5. 09-Apr-2026

    First On Board (Fob)

    Hon'ble Shri Justice Milind N. Jadhav

  6. 07-Apr-2026

    Hon'ble Shri Justice Milind N. JadhavView PDF

  7. 07-Apr-2026

    First On Board (Fob)

    Hon'ble Shri Justice Milind N. Jadhav

  8. 02-Apr-2026

    Hon'ble Shri Justice Milind N. JadhavView PDF

  9. 02-Apr-2026

    First On Board (Fob)

    Hon'ble Shri Justice Milind N. Jadhav

  10. 27-Mar-2026

    Hon'ble Shri Justice Milind N. JadhavView PDF

  11. 27-Mar-2026

    For Orders--

    Hon'ble Shri Justice Milind N. Jadhav

  12. 26-Mar-2026

    Hon'ble Shri Justice Milind N. JadhavView PDF

  13. 18-Dec-2025

    For Admission

    Hon'ble Shri Justice Milind N. Jadhav

  14. 11-Dec-2025

    Hon'ble Shri Justice Milind N. JadhavView PDF

  15. 11-Dec-2025

    First On Board (Fob)

    Hon'ble Shri Justice Milind N. Jadhav

  16. 04-Dec-2025

    Hon'ble Shri Justice Milind N. JadhavView PDF

  17. 04-Dec-2025

    First On Board (Fob)

    Hon'ble Shri Justice Milind N. Jadhav

  18. 27-Nov-2025

    Hon'ble Shri Justice Milind N. JadhavView PDF

  19. 27-Nov-2025

    First On Board (Fob)

    Hon'ble Shri Justice Milind N. Jadhav

  20. 27-Nov-2025

    For Admission

    Hon'ble Shri Justice Milind N. Jadhav

  21. 20-Nov-2025

    Hon'ble Shri Justice Milind N. JadhavView PDF

  22. 09-Oct-2025

    For Admission

    Hon'ble Shri Justice Milind N. Jadhav

  23. 25-Sep-2025

    Hon'ble Shri Justice Milind N. JadhavView PDF

  24. 26-Aug-2025

    First hearing

    Initial hearing scheduled

  25. 12-Jun-2025

    Hon'ble Ms. Justice Gauri GodseView PDF

  26. 28-May-2025

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

  27. 23-May-2025

    Case filed

    Registration No. IA/8391/2025

casestatus.in Summary

The Bombay High Court allowed the appeal and quashed the Municipal Corporation's notice and order for land acquisition, but on consent of both parties. The appellant agreed to surrender 3,127.43 sq.mtrs of land for a public road project connecting the Western Express Highway, with compensation payable under the Right to Fair Compensation and Transparency in Land Acquisition Act, 2013 instead of the Municipal Corporation Act. The State Government was directed to complete land acquisition proceedings within two months, and the Corporation may proceed with road construction pending acquisition completion. This case analysis is maintained by casestatus.in based on publicly available court records.