TUFAIL AHMED CHOUDHARY AND ORS vs THE STATE OF MAHARASHTRA THRUAUTHORITY AND ORS — WP/6977/2026

Case under Mah. Regional Town Planning Act Section NA. Disposed: Contested--Disposed Off on 03rd June 2026.

Case disposed

CNR: HCBM010258852026

Filing Number

WP/15086/2026

Filing Date

01-Jun-2026

Registration No

WP/6977/2026

Registration Date

02-Jun-2026

Judge

Hon'ble Shri Justice Shyam C. Chandak , Hon'ble Shri Justice Farhan Parvez Dubash

Coram

Hon'ble Shri Justice Shyam C. Chandak , Hon'ble Shri Justice Farhan Parvez Dubash

Bench Type

Division

Category

TOWN PLANNING ( 39 )

Sub-Category

OTHERS ( 99 )

Judicial Branch

Civil

Decision Date

03-Jun-2026

Nature of Disposal

Contested--Disposed Off

Last updated 04-Jun-2026

Acts & Sections

Mah. Regional Town Planning Act Section NA

Petitioner(s)

  1. 1.TUFAIL AHMED CHOUDHARY AND ORS

    Adv. VISHAL PATIL

  2. 2.NAIBHUNISA JAINUDDIN ANSARI

  3. 3.ANSARI MOHAMMAD JANUDDIN

  4. 4.SAFEENA BANO SHARIF AHMEDSHAIKH

  5. 5.GAZALA MOHAMMAD RAFIQUE SHAIKH

  6. 6.SADAT SUHAIL PAWLE

Respondent(s)

  1. 1.THE STATE OF MAHARASHTRA THRUAUTHORITY AND ORS

  2. 2.LD. DISTRICT COLLECTOR THANE

  3. 3.TAHASILDAR AND EXECUTIVE MAGISTRATE KALYAN

  4. 4.TALATHI, SAZA RAYA

Case History

  1. Case disposedDisposed

  2. 03-Jun-2026

    Hon'ble Shri Justice Shyam C. Chandak,hon'ble Shri Justice Farhan Parvez DubashView PDF

    The Bombay High Court disposed of the writ petition by directing petitioners to produce documents by June 9, 2026, establishing that a disputed structure is authorized and legal; the Tahsildar, Kalyan will then decide the matter within two weeks with no coercive action during this period. If petitioners fail to produce documents, they must demolish the structure within one week, otherwise authorities may proceed with demolition. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 03-Jun-2026

    For Circulation

    Hon'ble Shri Justice Shyam C. Chandak , Hon'ble Shri Justice Farhan Parvez Dubash

  4. 01-Jun-2026

    Case filed

    Registration No. WP/6977/2026

casestatus.in Summary

The Bombay High Court disposed of the writ petition by directing petitioners to produce documents by June 9, 2026, establishing that a disputed structure is authorized and legal; the Tahsildar, Kalyan will then decide the matter within two weeks with no coercive action during this period. If petitioners fail to produce documents, they must demolish the structure within one week, otherwise authorities may proceed with demolition. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts

Search Another Case