THE MUNICIPAL CORPORATION OF GREATER MUMBAI vs M/S. CASA PARADOX PVT. LTD. AND ORS. — HCBM10130872018

Case under Bombay Municipal Corporation Act Section 218D. Next hearing: 02nd April 2026.

Next hearing 02-Apr-2026

CNR: HCBM010130872018

Filing Number

FA/8362/2018

Filing Date

16-Mar-2018

Judge

Hon'ble Shri Justice Jitendra Shantilal Jain

Coram

Hon'ble Shri Justice Jitendra Shantilal Jain

Bench Type

Single

Category

FIRST APPEAL ( 53 )

Sub-Category

Against Order of Civil Court - Single Bench ( 7 )

Judicial Branch

Civil

Last updated 02-May-2026

Acts & Sections

Bombay Municipal Corporation Act Section 218D

Petitioner(s)

  1. 1.THE MUNICIPAL CORPORATION OF GREATER MUMBAI

    Adv. JERNOLD JOSEPH XAVIER

Respondent(s)

  1. 1.M/S. CASA PARADOX PVT. LTD. AND ORS.

  2. 2.SHRI. PRAKASH VALLABHDAS BHATIA-THROUGH HIS CONSTITUTED ATTORNEY MR.DIREN P.KHODA

  3. 3.RAGHUVANSHI MILLS LTD.

  4. 4.S.S.G. REALTORS AND DEVELOPERS PVT. LTD.

Case History

  1. 02-Apr-2026

    Next hearingPending

  2. 02-Apr-2026

    Hon'ble Shri Justice Jitendra Shantilal JainView PDF

    The Bombay High Court dismissed approximately 26 civil applications filed by the Municipal Corporation of Greater Mumbai seeking to condone delays of 1-9 years in filing appeals challenging demolition notices. The court found that the Corporation's explanation—that officers failed to report progress on cases following the 2017 Kamla Mills tragedy—did not constitute "sufficient cause" for such substantial delays, and that a subsequent incident cannot justify challenging old orders years later. However, the court granted the Corporation liberty to conduct fresh inspections and initiate new action based on current illegalities, while directing it to complete pending departmental proceedings against officers and superiors within 4 months and file a compliance report. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 02-Apr-2026

    For Orders (Due Matters)

    Hon'ble Shri Justice Jitendra Shantilal Jain

  4. 01-Apr-2026

    Hon'ble Shri Justice Jitendra Shantilal JainView PDF

  5. 01-Apr-2026

    First On Board (Fob)

    Hon'ble Shri Justice Jitendra Shantilal Jain

  6. 01-Apr-2026

    At 3.00 P.M.

    Hon'ble Shri Justice Jitendra Shantilal Jain

  7. 30-Mar-2026

    Hon'ble Shri Justice Jitendra Shantilal JainView PDF

  8. 18-Mar-2026

    Hon'ble Shri Justice Jitendra Shantilal JainView PDF

  9. 09-Mar-2026

    For Orders (Due Matters)

    Hon'ble Shri Justice Jitendra Shantilal Jain

  10. 24-Feb-2026

    Hon'ble Shri Justice Jitendra Shantilal JainView PDF

  11. 26-Sep-2025

    For Orders (Due Matters)

    Hon'ble Shri Justice M. M. Sathaye

  12. 04-Apr-2025

    For Direction

    Hon'ble Justice Sharmila U. Deshmukh

  13. 03-Apr-2025

    Hon'ble Justice Sharmila U. DeshmukhView PDF

  14. 24-Mar-2022

    First hearing

    Initial hearing scheduled

  15. 25-Sep-2018

    Hon'ble Smt. Justice Dr. Shalini Phansalkar-JoshiView PDF

  16. 16-Mar-2018

    Case filed

casestatus.in Summary

The Bombay High Court dismissed approximately 26 civil applications filed by the Municipal Corporation of Greater Mumbai seeking to condone delays of 1-9 years in filing appeals challenging demolition notices. The court found that the Corporation's explanation—that officers failed to report progress on cases following the 2017 Kamla Mills tragedy—did not constitute "sufficient cause" for such substantial delays, and that a subsequent incident cannot justify challenging old orders years later. However, the court granted the Corporation liberty to conduct fresh inspections and initiate new action based on current illegalities, while directing it to complete pending departmental proceedings against officers and superiors within 4 months and file a compliance report. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts

Search Another Case