GERA DEVELOPMENT PRIVATE LIMITED vs THE STATE OF MAHARASHTRA THR ITS SECRETARY DEPT AND ORS — WP/3151/2026
Case under Mah. Co-op. Soc. Act Section NA. Disposed: Contested--Dismissed on 01st April 2026.
CNR: HCBM010112362026
Filing Number
WP/6454/2026
Filing Date
06-Mar-2026
Registration No
WP/3151/2026
Registration Date
07-Mar-2026
Judge
Hon'ble Shri Justice Amit Borkar
Coram
Hon'ble Shri Justice Amit Borkar
Bench Type
Single
Category
ORDINARY CIVIL ( 30 )
Sub-Category
Cooperative Socities ( 103 )
Judicial Branch
Civil
Decision Date
01-Apr-2026
Nature of Disposal
Contested--Dismissed
Last updated 02-May-2026
Acts & Sections
Petitioner(s)
-
1.GERA DEVELOPMENT PRIVATE LIMITED
Adv. Manish Kelkar,SANDEEP PHATAK,SANDEEP PHATAK, ,SANDEEP PHATAK
Respondent(s)
-
1.THE STATE OF MAHARASHTRA THR ITS SECRETARY DEPT AND ORS
-
2.THE DIVISIONAL JOINT REGISTRAR
-
3.THE DISTRICT DEPUTY REGISTRAR
-
4.THE DEPUTY REGISTRAR, CO-OPERATIVE SOCIETIES, PUNE CITY(
-
5.PUNE (DR)
-
6.GERAS ISLE ROYALE CHS LTD
Case History
-
Case disposedDisposed
-
01-Apr-2026
Hon'ble Shri Justice Amit BorkarView PDF
Court Summary The Bombay High Court dismissed Gera Developers' writ petition challenging the formation of a single cooperative housing society for their multi-tower residential project. The court held that the developer's failure to initiate society formation within the statutory three-month deadline allowed unit holders (109 of 155, exceeding the 51% threshold) to proceed independently, and the integrated nature of the development with shared amenities justified one unified society rather than separate societies per tower. This case analysis is maintained by casestatus.in based on publicly available court records.
-
25-Mar-2026
Hon'ble Shri Justice Amit BorkarView PDF
-
25-Mar-2026
For Admission
Hon'ble Shri Justice Amit Borkar
-
16-Mar-2026
Hon'ble Shri Justice Amit BorkarView PDF
-
16-Mar-2026
For Circulation
Hon'ble Shri Justice Amit Borkar
-
09-Mar-2026
Hon'ble Shri Justice Amit BorkarView PDF
-
09-Mar-2026
First hearing
Initial hearing scheduled
-
06-Mar-2026
Case filed
Registration No. WP/3151/2026
Court Summary The Bombay High Court dismissed Gera Developers' writ petition challenging the formation of a single cooperative housing society for their multi-tower residential project. The court held that the developer's failure to initiate society formation within the statutory three-month deadline allowed unit holders (109 of 155, exceeding the 51% threshold) to proceed independently, and the integrated nature of the development with shared amenities justified one unified society rather than separate societies per tower. This case analysis is maintained by casestatus.in based on publicly available court records.