GRAM PANCHAYAT, MANEGAON THR AUTH SARPANCH SUNITA B SONAWANE AND ANR vs THE STATE OF MAHARASHTRA THR DEPT. OF RURAL AND REVENUE DEPT. AND ORS — WP/1837/2025
Case under Mah. Land Revenue Code, 1966 Section NA. Disposed: Contested--Disposed Off on 05th May 2026.
CNR: HCBM010058202025
Filing Number
WP/3528/2025
Filing Date
30-01-2025
Registration No
WP/1837/2025
Registration Date
06-02-2025
Judge
HON'BLE SHRI JUSTICE M. S. KARNIK , HON'BLE SHRI JUSTICE S. M. MODAK
Coram
HON'BLE SHRI JUSTICE M. S. KARNIK , HON'BLE SHRI JUSTICE S. M. MODAK
Bench Type
Division
Category
LAND LAWS AND AGRICULTURAL TENANCIES ( 21 )
Sub-Category
OTHERS ( 99 )
Judicial Branch
Civil
Decision Date
05th May 2026
Nature of Disposal
Contested--Disposed Off
Acts & Sections
Petitioner(s)
GRAM PANCHAYAT, MANEGAON THR AUTH SARPANCH SUNITA B SONAWANE AND ANR
Adv. Pramod Narayan Joshi
GRAM SABHA MANEGAON
SANJAY KACHARU SONAWANE
JAGAN THAKUJI KHOLAMBE
SOPAN RAMNATH SONAWANE
BHANUDAS VISHVANATH SONAWANE
YOGESG RANGANATH MALI
Respondent(s)
THE STATE OF MAHARASHTRA THR DEPT. OF RURAL AND REVENUE DEPT. AND ORS
TH CHIEG EXECUTIVE OFFICER ZILLA PARISHAD NASHIK
THE TAHSILDAR SINNAR
THE COLLECTOR NASHIK
THE MAHARSHTRA STATE ELECTRICITY DEVELOPMENT CORPORATION LTD
Adv. LITTLE AND COMPANY
Hearing History
Judge: HON'BLE SHRI JUSTICE M. S. KARNIK , HON'BLE SHRI JUSTICE S. M. MODAK
FOR CIRCULATION (URGENT ADMISSION)
FOR CIRCULATION
DUE ADMISSION - 1
DUE ADMISSION - 1
FOR ADMISSION
| Date | Purpose |
|---|---|
| 13-02-2025 | FOR CIRCULATION (URGENT ADMISSION) |
| 05-05-2026 | FOR CIRCULATION |
| 25-08-2025 | DUE ADMISSION - 1 |
| 11-07-2025 | DUE ADMISSION - 1 |
| 17-06-2025 | FOR ADMISSION |
Orders
Case Summary: WP/1837/2025 The Bombay High Court partially rejected the Gram Panchayat's challenge to a state solar energy project on government land (Gat No. 507), prioritizing public interest in renewable energy generation over mandatory consultation requirements under Section 8AA of the Maharashtra Village Panchayats Act. However, the court required compliance with consultation procedures before any acquisition of adjoining private/common land (Gat No. 506), ordering the Collector to decide within eight weeks after receiving the Gram Panchayat's views. This case analysis is maintained by casestatus.in based on publicly available court records.
Case Summary: WP/1837/2025 The Bombay High Court partially rejected the Gram Panchayat's challenge to a state solar energy project on government land (Gat No. 507), prioritizing public interest in renewable energy generation over mandatory consultation requirements under Section 8AA of the Maharashtra Village Panchayats Act. However, the court required compliance with consultation procedures before any acquisition of adjoining private/common land (Gat No. 506), ordering the Collector to decide within eight weeks after receiving the Gram Panchayat's views. This case analysis is maintained by casestatus.in based on publicly available court records.