GRAM PANCHAYAT, MANEGAON THR AUTH SARPANCH SUNITA B SONAWANE AND ANR vs THE STATE OF MAHARASHTRA THR DEPT. OF RURAL AND REVENUE DEPT. AND ORS — WP/1837/2025
Case under Mah. Land Revenue Code, 1966 Section NA. Disposed: Contested--Disposed Off on 05th May 2026.
CNR: HCBM010058202025
Filing Number
WP/3528/2025
Filing Date
30-Jan-2025
Registration No
WP/1837/2025
Registration Date
06-Feb-2025
Judge
Hon'ble Shri Justice M. S. Karnik , Hon'ble Shri Justice S. M. Modak
Coram
Hon'ble Shri Justice M. S. Karnik , Hon'ble Shri Justice S. M. Modak
Bench Type
Division
Category
LAND LAWS AND AGRICULTURAL TENANCIES ( 21 )
Sub-Category
OTHERS ( 99 )
Judicial Branch
Civil
Decision Date
05-May-2026
Nature of Disposal
Contested--Disposed Off
Last updated 10-Jun-2026
Acts & Sections
Petitioner(s)
-
1.GRAM PANCHAYAT, MANEGAON THR AUTH SARPANCH SUNITA B SONAWANE AND ANR
Adv. Pramod Narayan Joshi
-
2.GRAM SABHA MANEGAON
-
3.SANJAY KACHARU SONAWANE
-
4.JAGAN THAKUJI KHOLAMBE
-
5.SOPAN RAMNATH SONAWANE
-
6.BHANUDAS VISHVANATH SONAWANE
-
7.YOGESG RANGANATH MALI
Respondent(s)
-
1.THE STATE OF MAHARASHTRA THR DEPT. OF RURAL AND REVENUE DEPT. AND ORS
-
2.TH CHIEG EXECUTIVE OFFICER ZILLA PARISHAD NASHIK
-
3.THE TAHSILDAR SINNAR
-
4.THE COLLECTOR NASHIK
-
5.THE MAHARSHTRA STATE ELECTRICITY DEVELOPMENT CORPORATION LTD
Adv. LITTLE AND COMPANY
Case History
-
Case disposedDisposed
-
05-May-2026
Hon'ble Shri Justice M. S. Karnik,hon'ble Shri Justice S. M. ModakView PDF
Case Summary: WP/1837/2025 The Bombay High Court partially rejected the Gram Panchayat's challenge to a state solar energy project on government land (Gat No. 507), prioritizing public interest in renewable energy generation over mandatory consultation requirements under Section 8AA of the Maharashtra Village Panchayats Act. However, the court required compliance with consultation procedures before any acquisition of adjoining private/common land (Gat No. 506), ordering the Collector to decide within eight weeks after receiving the Gram Panchayat's views. This case analysis is maintained by casestatus.in based on publicly available court records.
-
05-May-2026
For Circulation
Hon'ble Shri Justice M. S. Karnik , Hon'ble Shri Justice S. M. Modak
-
17-Mar-2026
Hon'ble Shri Justice M. S. Karnik,hon'ble Shri Justice S. M. ModakView PDF
-
17-Mar-2026
Due Admission - 1
Hon'ble Shri Justice M. S. Karnik , Hon'ble Shri Justice S. M. Modak
-
16-Feb-2026
Hon'ble Shri Justice A.S. Gadkari,hon'ble Shri Justice Shyam C. ChandakView PDF
-
25-Aug-2025
Due Admission - 1
Hon'ble Shri Justice M. S. Karnik , Hon'ble Shri Justice N. R. Borkar
-
11-Jul-2025
Hon'ble Shri Justice M. S. Karnik,hon'ble Shri Justice N. R. BorkarView PDF
-
11-Jul-2025
Due Admission - 1
Hon'ble Shri Justice M. S. Karnik , Hon'ble Shri Justice N. R. Borkar
-
17-Jun-2025
Hon'ble Shri Justice M. S. Karnik,hon'ble Shri Justice N. R. BorkarView PDF
-
17-Jun-2025
For Admission
Hon'ble Shri Justice M. M. Sathaye , Hon'ble Shri Justice A.S. Chandurkar
-
13-Mar-2025
Hon'ble Shri Justice M. M. Sathaye,hon'ble Shri Justice A.S. ChandurkarView PDF
-
13-Feb-2025
Hon'ble Shri Justice M. M. Sathaye,hon'ble Shri Justice A.S. ChandurkarView PDF
-
13-Feb-2025
First hearing
Initial hearing scheduled
-
30-Jan-2025
Case filed
Registration No. WP/1837/2025
Case Summary: WP/1837/2025 The Bombay High Court partially rejected the Gram Panchayat's challenge to a state solar energy project on government land (Gat No. 507), prioritizing public interest in renewable energy generation over mandatory consultation requirements under Section 8AA of the Maharashtra Village Panchayats Act. However, the court required compliance with consultation procedures before any acquisition of adjoining private/common land (Gat No. 506), ordering the Collector to decide within eight weeks after receiving the Gram Panchayat's views. This case analysis is maintained by casestatus.in based on publicly available court records.