RAJENDRA CHANDULAL SHAH vs STATE OF MAHARASHTRA THR. ITS PRINCIPAL SECRETARY URBAN DEVELOPMENT DEPARTMENT AND ORS — WP/5195/2026

Case under Right to Fair Compensation & Transparency in Land Acquisition,rehabilitation & Resettlement Act,2013 Section NA. Disposed: Contested--Disposed Off on 23rd April 2026.

CNR: HCBM010007082026

CASE DISPOSED

Filing Number

WP/443/2026

Filing Date

07-01-2026

Registration No

WP/5195/2026

Registration Date

17-04-2026

Judge

HON'BLE SHRI JUSTICE MANISH PITALE , HON'BLE SHRI JUSTICE SHREERAM VINAYAK SHIRSAT

Coram

HON'BLE SHRI JUSTICE MANISH PITALE , HON'BLE SHRI JUSTICE SHREERAM VINAYAK SHIRSAT

Bench Type

Division

Category

ORDINARY CIVIL ( 30 )

Sub-Category

Project Affected Persons ( 100 )

Judicial Branch

Civil

Decision Date

23rd April 2026

Nature of Disposal

Contested--Disposed Off

Acts & Sections

Right to Fair Compensation & Transparency in Land Acquisition,rehabilitation & Resettlement Act,2013 Section NA

Petitioner(s)

RAJENDRA CHANDULAL SHAH

Adv. F N Momin

Respondent(s)

STATE OF MAHARASHTRA THR. ITS PRINCIPAL SECRETARY URBAN DEVELOPMENT DEPARTMENT AND ORS

BHIWANDI NIZAMPUR CITY MUNICIPAL CORPORATION

ASSISTANT DIRECTOR OF TOWN PLANNING

Hearing History

Judge: HON'BLE SHRI JUSTICE MANISH PITALE , HON'BLE SHRI JUSTICE SHREERAM VINAYAK SHIRSAT

09-02-2026

OBJECTIONS TO BE REMOVED

23-04-2026

FRESH ADMISSION

Orders

23-04-2026
HON'BLE SHRI JUSTICE MANISH PITALE,HON'BLE SHRI JUSTICE SHREERAM VINAYAK SHIRSAT

The Bombay High Court disposed of multiple consolidated writ petitions filed by shop owners whose establishments were demolished during a road-widening project in Bhiwandi. The petitioners claimed they were not compensated for the demolitions. The court found merit in the municipal corporation's contention that the matter could be resolved through a time-bound process and directed the Bhiwandi Nizampur City Municipal Corporation to decide the petitioners' representations within eight weeks in accordance with law. This case analysis is maintained by casestatus.in based on publicly available court records.

casestatus.in Summary

The Bombay High Court disposed of multiple consolidated writ petitions filed by shop owners whose establishments were demolished during a road-widening project in Bhiwandi. The petitioners claimed they were not compensated for the demolitions. The court found merit in the municipal corporation's contention that the matter could be resolved through a time-bound process and directed the Bhiwandi Nizampur City Municipal Corporation to decide the petitioners' representations within eight weeks in accordance with law. This case analysis is maintained by casestatus.in based on publicly available court records.