M/S DIPAK ENTERPRISE vs THE STATE OF ASSAM AND 5 ORS Advocate - GA, ASSAM, ,SC, FINANCE — WP(C)/5031/2024

Case under Constitution of India Section 226. Disposed: Contested--Disposed Of on 06th May 2026.

Case disposed

CNR: GAHC010199802024

Filing Number

WP(C)/11227/2024

Filing Date

20-Sep-2024

Registration No

WP(C)/5031/2024

Registration Date

25-Sep-2024

Judge

Honourable Mr. Justice Devashis Baruah

Coram

Honourable Mr. Justice Devashis Baruah

Bench Type

Single Bench

Category

10180 - Award of contracts by the State or its instrumentalities ( 172 )

Judicial Branch

Writ Section

Decision Date

06-May-2026

Nature of Disposal

Contested--Disposed Of

Last updated 10-Jun-2026

Acts & Sections

Constitution of India Section 226

Petitioner(s)

  1. 1.M/S DIPAK ENTERPRISE

    Adv. MR. P N SHARMA,M SHARMA,M SHARMA, ,MR. S UPADHAYA,M SHARMA

Respondent(s)

  1. 1.THE STATE OF ASSAM AND 5 ORS Advocate - GA (Government Advocate), ASSAM, ,SC, FINANCE

  2. 2.COMMISSIONER AND SECRETARY

  3. 3.THE COMMISSIONER AND SECRETARY

  4. 4.THE DIRECTOR GENERAL OF POLICE

  5. 5.THE INSPECTOR GENERAL OF POLICE (A)

  6. 6.THE SUPERINTENDENT OF POLICE

Case History

  1. Case disposedDisposed

  2. 06-May-2026

    Honourable Mr. Justice Devashis BaruahView PDF

    Case Summary: M/S DIPAK ENTERPRISE v. STATE OF ASSAM WP(C)/5031/2024 | Gauhati High Court | Judgment Date: 06.05.2026 The court directed Assam Police authorities to verify and complete payment to contractor Dipak Enterprise for three completed construction works (vehicle garages and store room at MT Branch, Goalpara) totaling Rs. 13,62,172, which remained unpaid for nearly four years despite work completion certificates and administrative approval. The court held that if verification confirms successful execution and submission of requisite documents, authorities must release the dues within six months. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 05-Sep-2025

    Honourable Mr. Justice Kardak EteView PDF

  4. 27-Sep-2024

    Honourable Mr. Justice Michael ZothankhumaView PDF

  5. 20-Sep-2024

    Case filed

    Registration No. WP(C)/5031/2024

casestatus.in Summary

Case Summary: M/S DIPAK ENTERPRISE v. STATE OF ASSAM WP(C)/5031/2024 | Gauhati High Court | Judgment Date: 06.05.2026 The court directed Assam Police authorities to verify and complete payment to contractor Dipak Enterprise for three completed construction works (vehicle garages and store room at MT Branch, Goalpara) totaling Rs. 13,62,172, which remained unpaid for nearly four years despite work completion certificates and administrative approval. The court held that if verification confirms successful execution and submission of requisite documents, authorities must release the dues within six months. This case analysis is maintained by casestatus.in based on publicly available court records.