M/S DIPAK ENTERPRISE vs THE STATE OF ASSAM AND 5 ORS Advocate - GA, ASSAM, ,SC, FINANCE — WP(C)/5031/2024
Case under Constitution of India Section 226. Disposed: Contested--Disposed Of on 06th May 2026.
CNR: GAHC010199802024
Filing Number
WP(C)/11227/2024
Filing Date
20-Sep-2024
Registration No
WP(C)/5031/2024
Registration Date
25-Sep-2024
Judge
Honourable Mr. Justice Devashis Baruah
Coram
Honourable Mr. Justice Devashis Baruah
Bench Type
Single Bench
Category
10180 - Award of contracts by the State or its instrumentalities ( 172 )
Judicial Branch
Writ Section
Decision Date
06-May-2026
Nature of Disposal
Contested--Disposed Of
Last updated 10-Jun-2026
Acts & Sections
Petitioner(s)
-
1.M/S DIPAK ENTERPRISE
Adv. MR. P N SHARMA,M SHARMA,M SHARMA, ,MR. S UPADHAYA,M SHARMA
Respondent(s)
-
1.THE STATE OF ASSAM AND 5 ORS Advocate - GA (Government Advocate), ASSAM, ,SC, FINANCE
-
2.COMMISSIONER AND SECRETARY
-
3.THE COMMISSIONER AND SECRETARY
-
4.THE DIRECTOR GENERAL OF POLICE
-
5.THE INSPECTOR GENERAL OF POLICE (A)
-
6.THE SUPERINTENDENT OF POLICE
Case History
-
Case disposedDisposed
-
06-May-2026
Honourable Mr. Justice Devashis BaruahView PDF
Case Summary: M/S DIPAK ENTERPRISE v. STATE OF ASSAM WP(C)/5031/2024 | Gauhati High Court | Judgment Date: 06.05.2026 The court directed Assam Police authorities to verify and complete payment to contractor Dipak Enterprise for three completed construction works (vehicle garages and store room at MT Branch, Goalpara) totaling Rs. 13,62,172, which remained unpaid for nearly four years despite work completion certificates and administrative approval. The court held that if verification confirms successful execution and submission of requisite documents, authorities must release the dues within six months. This case analysis is maintained by casestatus.in based on publicly available court records.
-
05-Sep-2025
Honourable Mr. Justice Kardak EteView PDF
-
27-Sep-2024
Honourable Mr. Justice Michael ZothankhumaView PDF
-
20-Sep-2024
Case filed
Registration No. WP(C)/5031/2024
Case Summary: M/S DIPAK ENTERPRISE v. STATE OF ASSAM WP(C)/5031/2024 | Gauhati High Court | Judgment Date: 06.05.2026 The court directed Assam Police authorities to verify and complete payment to contractor Dipak Enterprise for three completed construction works (vehicle garages and store room at MT Branch, Goalpara) totaling Rs. 13,62,172, which remained unpaid for nearly four years despite work completion certificates and administrative approval. The court held that if verification confirms successful execution and submission of requisite documents, authorities must release the dues within six months. This case analysis is maintained by casestatus.in based on publicly available court records.