M/S WIN POWER INFRACON LLP AND ORS vs ASSAM POWER DISTRIBUTION COMPANY LIMITED AND ORS Advocate - SC, APDCL, ,FOR CAVEATOR,MR. K P PATHAK,MR BHARGAV DAS — WP(C)/1632/2026
Case under Constitution of India Section 226. Disposed: Contested--Disposed Of on 07th May 2026.
CNR: GAHC010056982026
e-Filing Number
16-03-2026
Filing Number
WP(C)/3196/2026
Filing Date
17-Mar-2026
Registration No
WP(C)/1632/2026
Registration Date
17-Mar-2026
Judge
Honourable Mr. Justice Devashis Baruah
Coram
Honourable Mr. Justice Devashis Baruah
Bench Type
Single Bench
Category
10180 - Award of contracts by the State or its instrumentalities ( 172 )
Judicial Branch
Writ Section
Decision Date
07-May-2026
Nature of Disposal
Contested--Disposed Of
Last updated 09-Jun-2026
Acts & Sections
Petitioner(s)
-
1.M/S WIN POWER INFRACON LLP AND ORS
Adv. MR D NANDI,M. KUMARI,M. KUMARI, ,MS P MAZUMDAR,MS. M KUMARI,MR K K MAHANTA (Sr. Advocate),MS P MAZUMDAR,M. KUMARI
-
2.SHRI AMRENDRA KUMAR TIWARI
Respondent(s)
-
1.ASSAM POWER DISTRIBUTION COMPANY LIMITED AND ORS Advocate - SC, APDCL, ,FOR CAVEATOR,MR. K P PATHAK,MR BHARGAV DAS
-
2.CHAIRMAN APDCL
-
3.MANAGING DIRECTOR APDCL
-
4.CHIEF GENERAL MANAGER (DISTRIBUTION AND SAFETY)
-
5.CHIEF GENERAL MANAGER (AUDIT)
Case History
-
Case disposedDisposed
-
07-May-2026
Honourable Mr. Justice Devashis BaruahView PDF
-
07-May-2026
Honourable Mr. Justice Devashis BaruahView PDF
CASE SUMMARY: WP(C)/1632/2026 Court: Gauhati High Court Date: 07.05.2026 Decision: Petition dismissed. The court held that the Letter of Intent was not a concluded contract and that rejection of the petitioner's bid for non-compliance with bid capacity requirements was justified. Key Findings: - Petitioner Win Power Infracon LLP submitted a construction tender bid of Rs 9,99,31,159 (19.97% below estimate), making it technically lowest bidder. - The letter of intent issued Feb 5, 2026 was merely an "embryonic promise," not a binding contract, pending formal Letter of Acceptance. - Petitioner failed to submit required supporting documents for bid capacity proof (Annexure-1E) at bid submission deadline; these were submitted only later on Feb 10, 2026. - Court found the rejection justified as an essential tender requirement (proving adequate bid capacity per Clause 15(iii)) was violated, protecting competitive fairness among seven bidders. This case analysis is maintained by casestatus.in based on publicly available court records.
-
07-May-2026
Admission
Honourable Mr. Justice Devashis Baruah
-
06-May-2026
Motion
Honourable Mr. Justice Manish Choudhury
-
05-May-2026
Honourable Mr. Justice Devashis BaruahView PDF
-
05-May-2026
Admission
Honourable Mr. Justice Devashis Baruah
-
24-Apr-2026
Honourable Mr. Justice Devashis BaruahView PDF
-
27-Mar-2026
Honourable Mr. Justice Manish ChoudhuryView PDF
-
27-Mar-2026
First hearing
Initial hearing scheduled
-
18-Mar-2026
Honourable Mr. Justice Manish ChoudhuryView PDF
-
17-Mar-2026
Case filed
Registration No. WP(C)/1632/2026
CASE SUMMARY: WP(C)/1632/2026 Court: Gauhati High Court Date: 07.05.2026 Decision: Petition dismissed. The court held that the Letter of Intent was not a concluded contract and that rejection of the petitioner's bid for non-compliance with bid capacity requirements was justified. Key Findings: - Petitioner Win Power Infracon LLP submitted a construction tender bid of Rs 9,99,31,159 (19.97% below estimate), making it technically lowest bidder. - The letter of intent issued Feb 5, 2026 was merely an "embryonic promise," not a binding contract, pending formal Letter of Acceptance. - Petitioner failed to submit required supporting documents for bid capacity proof (Annexure-1E) at bid submission deadline; these were submitted only later on Feb 10, 2026. - Court found the rejection justified as an essential tender requirement (proving adequate bid capacity per Clause 15(iii)) was violated, protecting competitive fairness among seven bidders. This case analysis is maintained by casestatus.in based on publicly available court records.
Explore other courts