JAYAVARAPU NAGA VENKATA RAO vs BALABHADRAPU VEERABHADRA RAO Advocate - V V SATISH (SC for APEPDCL) — CC/673/2025
Case under Contempt of Courts Act, 1971 Section 10 to 12. Disposed: Uncontested--DISMISSED NO COSTS on 31st March 2026.
CNR: APHC010089282025
Filing Number
CC/6602/2025
Filing Date
19-Feb-2025
Registration No
CC/673/2025
Registration Date
10-Mar-2025
Judge
Subba Reddy Satti
Coram
Subba Reddy Satti
Bench Type
Single Bench
Judicial Branch
OS Section
Decision Date
31-Mar-2026
Nature of Disposal
Uncontested--DISMISSED NO COSTS
Last updated 27-Apr-2026
Acts & Sections
Petitioner(s)
-
1.JAYAVARAPU NAGA VENKATA RAO
Adv. VIJAYA KUMAR SATA
Respondent(s)
-
1.BALABHADRAPU VEERABHADRA RAO Advocate - V V SATISH (SC for APEPDCL)
-
2.Kolli Ratnala Rao,
Adv. V V SATISH (SC for APEPDCL)
-
3.KRANTHi CONSTRUCTiONS Civil
Case History
-
Case disposedDisposed
-
31-Mar-2026
Subba Reddy SattiView PDF
Case Summary The High Court of Andhra Pradesh dismissed the contempt case filed against APEPDCL officials and a contractor. The court found no willful disobedience of the interim order dated 12.08.2024 because: (1) the interim order only suspended the Executive Engineer's communication, not the contractor's termination proceedings; (2) no specific direction was issued to re-engage the petitioner; and (3) the underlying writ petition was dismissed on 02.03.2026, causing the interim order to automatically cease to exist and merge with the final order. This case analysis is maintained by casestatus.in based on publicly available court records.
-
05-Mar-2026
Subba Reddy SattiView PDF
-
05-Mar-2026
For Admission
Subba Reddy Satti
-
12-Feb-2026
Subba Reddy SattiView PDF
-
12-Feb-2026
For Admission
Subba Reddy Satti
-
22-Jan-2026
Subba Reddy SattiView PDF
-
09-Jan-2026
For Admission
Subba Reddy Satti
-
08-Jan-2026
Subba Reddy SattiView PDF
-
12-Dec-2025
Subba Reddy SattiView PDF
-
04-Apr-2025
K Manmadha RaoView PDF
-
21-Mar-2025
Subba Reddy SattiView PDF
-
21-Mar-2025
Subba Reddy SattiView PDF
-
17-Mar-2025
First hearing
Initial hearing scheduled
-
19-Feb-2025
Case filed
Registration No. CC/673/2025
Case Summary The High Court of Andhra Pradesh dismissed the contempt case filed against APEPDCL officials and a contractor. The court found no willful disobedience of the interim order dated 12.08.2024 because: (1) the interim order only suspended the Executive Engineer's communication, not the contractor's termination proceedings; (2) no specific direction was issued to re-engage the petitioner; and (3) the underlying writ petition was dismissed on 02.03.2026, causing the interim order to automatically cease to exist and merge with the final order. This case analysis is maintained by casestatus.in based on publicly available court records.
Explore other courts