M/S JEEVAN CONSTRUCTION COMPANY vs ENGINEER IN CHIEF, U.P. PUBLIC WORKS DEPARTMENT AND 3 OTHERS — ARCO/175/2024

Next hearing: 19th May 2026.

Next hearing 19-May-2026

CNR: UPHC015495132024

Filing Number

ARCO/216581/2024

Filing Date

17-Oct-2024

Registration No

ARCO/175/2024

Registration Date

13-Nov-2024

Judge

Piyush Agrawal

Coram

Piyush Agrawal

Bench Type

Single Bench

Judicial Branch

Civil Misc.

Last updated 26-Jun-2026

Petitioner(s)

  1. 1.M/S JEEVAN CONSTRUCTION COMPANY

    Adv. SUDHIR DIXIT,ANUPAM SHYAM DWIVEDI,ANUPAM SHYAM DWIVEDI, ,UTKARSH DIXIT,ANUPAM SHYAM DWIVEDI

Respondent(s)

  1. 1.ENGINEER IN CHIEF, U.P. PUBLIC WORKS DEPARTMENT AND 3 OTHERS

    Adv. ,C.S.C. 1123

  2. 2.CHAIRMAN OF THE EXECUTIVE COMMITTEE, INDIAN ROADS CONGRESS

    Adv. C.S.C.

  3. 3.EXECUTIVE ENGINEER, PROVISIONAL DIVISIONAL, P.W.D.

    Adv. C.S.C.

  4. 4.SUPERINTENDING ENGINEER, AGRA CIRCLE, P.W.D.

    Adv. C.S.C.

Case History

  1. 19-May-2026

    Next hearingPending

  2. 26-May-2026

    Piyush Agrawal

  3. 19-May-2026

    Piyush Agrawal

  4. 07-May-2026

    Piyush AgrawalView PDF

    In this Arbitration and Conciliation Application (U/S 11(4)) filed by M/S Jeevan Construction Company against the Engineer In Chief, U.P. Public Works Department and 3 others, the High Court at Allahabad accepted the rejoinder affidavit filed by the applicant on May 7, 2026. The case was adjourned and listed for further hearing on May 19, 2026, with no final order on merits issued at this stage. This case analysis is maintained by casestatus.in based on publicly available court records.

  5. 07-May-2026

    Piyush Agrawal

  6. 28-Apr-2026

    Piyush AgrawalView PDF

  7. 28-Apr-2026

    Piyush Agrawal

  8. 09-Apr-2026

    Piyush AgrawalView PDF

  9. 09-Apr-2026

    Piyush Agrawal

  10. 11-Mar-2026

    Piyush AgrawalView PDF

  11. 11-Mar-2026

    Revoked

    Piyush Agrawal

  12. 16-Dec-2025

    Piyush AgrawalView PDF

  13. 05-Dec-2025

    Piyush Agrawal

  14. 03-Jan-2025

    Manoj Kumar Gupta

  15. 20-Dec-2024

    Manoj Kumar Gupta

  16. 13-Dec-2024

    Manoj Kumar GuptaView PDF

  17. 13-Dec-2024

    Manoj Kumar Gupta

  18. 06-Dec-2024

    Manoj Kumar GuptaView PDF

  19. 06-Dec-2024

    Manoj Kumar Gupta

  20. 29-Nov-2024

    First hearing

    Initial hearing scheduled

  21. 17-Oct-2024

    Case filed

    Registration No. ARCO/175/2024

casestatus.in Summary

In this Arbitration and Conciliation Application (U/S 11(4)) filed by M/S Jeevan Construction Company against the Engineer In Chief, U.P. Public Works Department and 3 others, the High Court at Allahabad accepted the rejoinder affidavit filed by the applicant on May 7, 2026. The case was adjourned and listed for further hearing on May 19, 2026, with no final order on merits issued at this stage. This case analysis is maintained by casestatus.in based on publicly available court records.