IN THE SUPREME COURT OF INDIA CIVIL ORIGINAL JURISDICTION
ARBITRATION PETITION NO.73/2025
INDRA SISTEMAS S.A ...PETITIONER
VERSUS
KOLKATA METRO RAIL CORPORATION LTD. ...RESPONDENT
O R D E R
1. We have heard the learned counsel for the parties
and perused the record.
2. By way of the instant petition under Section 11(6)
of the Arbitration and Conciliation Act, 1996 (“Act”),
the Petitioner seeks appointment of the Respondent’s
Nominee Arbitrator as well as the third/presiding
Arbitrator. Such appointment is sought under Clause 17.9
of the General Conditions of Contract (“GCC”), as
amended by Clause 49B of the Special Conditions of
Contract (“SCC”), which form part of the Contract
Agreement dated 10.09.2014 (“Contract”) entered into
between the parties.
3. To broadly set out the sequence of events, the
Petitioner is a company registered under the laws of
1
Spain and engaged in the business of metro rail traffic
management and fare collection systems, while the
Respondent is a Government of India enterprise
implementing the Kolkata (East-West Metro) Corridor
Project (“Project”).
4. Under the Contract, the Petitioner was entrusted
with the design, manufacture, supply, installation,
testing and commissioning of the Automatic Fare
Collection (AFC) System for the Project. The works under
the Contract were structured in two phases, namely...