ITEM NO.7 COURT NO.1 SECTION XI-A
S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS
SPECIAL LEAVE PETITION (CIVIL) Diary No.47889/2023
(Arising out of impugned final judgment and order dated 10-11-2022 in WP(C) No.31673/2021 passed by the High Court of Orissa at Cuttack)
THE STATE OF ODISHA & ORS. Petitioner(s)
VERSUS
M/S. SBM NIRMAN CONSTRUCTION PVT. LIMITED Respondent(s)
(With IA No.251149/2023-CONDONATION OF DELAY IN FILING)
Date : 13-12-2023 This petition was called on for hearing today.
CORAM : HON'BLE THE CHIEF JUSTICE HON'BLE MR. JUSTICE J.B. PARDIWALA HON'BLE MR. JUSTICE MANOJ MISRA
For Petitioner(s) Ms. Anindita Pujari, AOR Mr. Shileshwar Yadav, Adv. Ms. Radhika Mohapatra, Adv. Ms. Bhumika Chouksey, Adv. For Respondent(s)
UPON hearing the counsel the Court made the following O R D E R
1 There is a delay of 283 days in filing the Special Leave Petition. The
explanation for the delay is not sufficient. Consequently, the Special Leave
Petition is dismissed on the ground of delay.
(CHETAN KUMAR) (SAROJ KUMARI GAUR) A.R.-cum-P.S. Assistant Registrar