ITEM NO.22 (MM) COURT NO.15 SECTION XIV

S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS

Special Leave to Appeal (C) No(s). 23322-23329/2022

[Arising out of impugned final judgment and order dated 08-09-2022 in LPA No. 457/2012 08-09-2022 in LPA No. 473/2012 08-09-2022 in LPA No. 474/2012 08-09-2022 in LPA No. 475/2012 08-09-2022 in LPA No. 476/2012 08-09-2022 in LPA No. 479/2012 08-09-2022 in LPA No. 463/2012 08-09-2022 in LPA No. 472/2012 passed by the High Court of Himachal Pradesh at Shimla]

THE GENERAL MANAGER CHAMERA HYDROELECTRIC PROJECT Petitioner(s)

VERSUS

GANDHI RAM Respondent(s)

Date : 10-12-2024 These petitions were called on for hearing today.

CORAM : HON'BLE MR. JUSTICE DIPANKAR DATTA HON'BLE MR. JUSTICE PRASHANT KUMAR MISHRA

For Petitioner(s) Mr. Jayant K Sud, Sr. Adv. Ms. Hetu Arora Sethi, AOR Ms. Lalit Mohini Bhat, Adv. Ms. Saumya Tandon, Adv. Mr. Siddarth Agarwal, Adv. For Respondent(s) Mr. Gaurav Agrawal, Sr. Adv. Mr. Rohan Thawani, Adv. Mr. C. George Thomas, AOR Mr. Ansh Mittal, Adv.

UPON hearing the counsel the Court made the following O R D E R

Relist...